
Earned Value Management (EVM) - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
8 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the Cost Performance Index (CPI) indicate in Earned Value Management?
Schedule deviation from the plan
The cost of completing the remaining work
Cost efficiency of the work performed
The time needed to complete the project
Answer explanation
CPI = EV ÷ AC and shows how efficiently the budget is being used. A CPI of 1 means on budget; greater than 1 means under budget; less than 1 means over budget.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the correct formula for Schedule Variance (SV)?
SV = AC - PV
SV = EV - PV
SV = EV - AC
SV = PV - EV
Answer explanation
Schedule Variance indicates how much ahead or behind schedule the project is. It compares earned value to planned value.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Your project has the following values:
Planned Value (PV) = $200,000
Earned Value (EV) = $180,000
Actual Cost (AC) = $190,000
What is the Schedule Performance Index (SPI)?
0.95
1.05
0.90
1.10
Answer explanation
SPI = EV ÷ PV = 180,000 ÷ 200,000 = 0.90. This means the project is progressing at 90% of the planned schedule.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You’re tracking the performance of a construction project. The EV is $250,000 and the AC is $275,000. What does the Cost Variance (CV) tell you?
The project is ahead of budget
The project is under budget
The project is on budget
The project is over budget
Answer explanation
CV = EV - AC = $250,000 - $275,000 = -$25,000. A negative value indicates a cost overrun.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does a To-Complete Performance Index (TCPI) greater than 1.0 indicate?
The project is performing ahead of schedule
The remaining work must be performed more efficiently than planned
The project is under budget
No additional performance improvement is required
Answer explanation
A TCPI > 1 indicates the project must improve cost efficiency to meet the budget.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are working on a bridge construction project. You find the following:
BAC = $500,000
EV = $300,000
AC = $350,000
What is the CPI, and what does it mean?
1.17; project is under budget
0.86; project is over budget
1.17; project is over budget
0.86; project is under budget
Answer explanation
CPI = EV ÷ AC = $300,000 ÷ $350,000 = 0.86. Since CPI < 1, the project is over budget.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which EVM term represents the budgeted cost of work scheduled to be done?
Earned Value (EV)
Actual Cost (AC)
Planned Value (PV)
Schedule Performance Index (SPI)
Answer explanation
PV is the budgeted amount for the work planned to be done up to a specific point in time.
8.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are evaluating two projects. Project A has a CPI of 1.10, and Project B has a CPI of 0.95.
Which statement is correct?
Project A is over budget
Project B is under budget
Project A is more cost-efficient than Project B
Both projects are equally efficient
Answer explanation
A CPI greater than 1 indicates better cost efficiency. Therefore, Project A is performing more efficiently than Project B.
Similar Resources on Wayground
10 questions
PMP PROJECT COMMUNICATIONS MANAGEMENT

Quiz
•
Professional Development
10 questions
PMP Perjuangan Chapter 7 Cost Management

Quiz
•
Professional Development
5 questions
Expected Monetary Value (EMV) - Assignment

Quiz
•
Professional Development
12 questions
Project Management Master Class 2

Quiz
•
Professional Development
5 questions
EAC, ETC, VAC - Assignment

Quiz
•
Professional Development
10 questions
Managing Projects

Quiz
•
Professional Development
8 questions
Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz
•
Professional Development
10 questions
PMP - PROJECT INTEGRATION

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade