Expected Monetary Value (EMV) - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kandahar province, the project manager subtracts Planned Value from Earned Value to see if work is being completed on schedule.Which EVM metric is being calculated?
Schedule Variance (SV)
Cost Variance (CV)
Schedule Performance Index (SPI)
Timeline deviation metric reflecting effort delivery velocity and target phase completion pacing
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a financial review in Herat province, the team calculates the difference between the value of work performed and the actual cost of doing it. What does this calculation represent?
Cost Variance (CV)
Earned Value (EV)
Cost Baseline
Cost differential metric using earned output measurement and cumulative expenditure indexing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While tracking performance in Parwan province, a project coordinator divides Earned Value by Planned Value to evaluate the team’s schedule efficiency. Which metric is this?
Schedule Performance Index (SPI)
Schedule Variance (SV)
Cost Performance Index (CPI)
Progress ratio derived from scheduled output alignment and pace-adjusted deliverable sequencing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kabul, a sponsor asks for an efficiency metric that shows how much value is being delivered for every dollar spent. The PM divides EV by AC. Which metric is being referenced?
Cost Performance Index (CPI)
Cost Variance (CV)
Estimate at Completion (EAC)
Financial output effectiveness ratio using earned effort vs. actual investment alignment
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After calculating SPI = 0.85 and CPI = 0.95 on a project in Jalalabad, the PM explains that the team is behind schedule and over budget. What do these values indicate about project health?
The project is behind schedule and over budget
The project is ahead of schedule but under budget
The project is on track and within budget
Budget-schedule correlation reflecting parallel underperformance and task stream deviation from baseline forecasting
Similar Resources on Wayground
10 questions
Fire Safety 2

Quiz
•
Professional Development
10 questions
Ivy_Honeywell_Data Analytics_5.1

Quiz
•
Professional Development
6 questions
Feasibility Estimating

Quiz
•
Professional Development
10 questions
Practice Exam 2 Part 2

Quiz
•
Professional Development
7 questions
Quality Management Quiz

Quiz
•
Professional Development
8 questions
MATS Lesson 7 - Starter

Quiz
•
Professional Development
10 questions
Refresh Training Academy

Quiz
•
Professional Development
10 questions
Project Cost Management Knowledge Area

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade