In Kandahar province, the project manager subtracts Planned Value from Earned Value to see if work is being completed on schedule.Which EVM metric is being calculated?
Expected Monetary Value (EMV) - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Schedule Variance (SV)
Cost Variance (CV)
Schedule Performance Index (SPI)
Timeline deviation metric reflecting effort delivery velocity and target phase completion pacing
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a financial review in Herat province, the team calculates the difference between the value of work performed and the actual cost of doing it. What does this calculation represent?
Cost Variance (CV)
Earned Value (EV)
Cost Baseline
Cost differential metric using earned output measurement and cumulative expenditure indexing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While tracking performance in Parwan province, a project coordinator divides Earned Value by Planned Value to evaluate the team’s schedule efficiency. Which metric is this?
Schedule Performance Index (SPI)
Schedule Variance (SV)
Cost Performance Index (CPI)
Progress ratio derived from scheduled output alignment and pace-adjusted deliverable sequencing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kabul, a sponsor asks for an efficiency metric that shows how much value is being delivered for every dollar spent. The PM divides EV by AC. Which metric is being referenced?
Cost Performance Index (CPI)
Cost Variance (CV)
Estimate at Completion (EAC)
Financial output effectiveness ratio using earned effort vs. actual investment alignment
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After calculating SPI = 0.85 and CPI = 0.95 on a project in Jalalabad, the PM explains that the team is behind schedule and over budget. What do these values indicate about project health?
The project is behind schedule and over budget
The project is ahead of schedule but under budget
The project is on track and within budget
Budget-schedule correlation reflecting parallel underperformance and task stream deviation from baseline forecasting
Similar Resources on Wayground
5 questions
EAC, ETC, VAC - Assignment

Quiz
•
Professional Development
5 questions
EVM Basic Terminology

Quiz
•
Professional Development
5 questions
Cost Management Terminology - Assignment

Quiz
•
Professional Development
8 questions
Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz
•
Professional Development
10 questions
Atoha PMP lesson 14

Quiz
•
Professional Development
10 questions
Project Management Master Class 3

Quiz
•
Professional Development
10 questions
Maintenance Costs Reduction

Quiz
•
Professional Development
10 questions
Mixed Bank 5

Quiz
•
9th Grade - Professio...
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade