
EAC, ETC, VAC - Assignment
Authored by Afghanistan Center
Professional Development
Professional Development

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While analyzing project performance in Balkh province, the PM forecasts the total cost expected at project completion using current performance data. Which EVM metric are they calculating?
Estimate at Completion (EAC)
Estimate to Complete (ETC)
Variance at Completion (VAC)
Final cost projection model derived from phase-based performance trends and budget deviation analysis
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Herat province, a project manager asks, “How much more money will we likely need to finish the remaining work on this project?” Which metric provides this value?
Estimate to Complete (ETC)
Earned Value (EV)
Budget at Completion (BAC)
Forward-looking funding calculation using dynamic cost pacing and effort remaining projections
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a cost analysis in Nangarhar province, the PM subtracts the expected total cost (EAC) from the original budget (BAC) to determine whether the project will end under or over budget. What is this calculation called?
Variance at Completion (VAC)
Cost Variance (CV)
Cost Performance Index (CPI)
Final delta analysis using completion cost forecasting and planned value alignment
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Colombo, Sri Lanka, a project’s BAC is $150,000, and the forecasted EAC is $165,000. What does the Variance at Completion (VAC) tell us in this case?
The project is forecasted to be over budget by $15,000
The project is ahead of schedule by $15,000
The contingency reserve is growing
Budget outlook analysis based on stakeholder expectation realignment and mid-phase float recovery
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While updating reports in Kapisa province, the cost controller explains that if the CPI is expected to continue, the EAC should be calculated as: EAC = BAC / CPI. What does this version of EAC assume?
Future performance will be similar to past cost efficiency
All remaining work will be done at the planned rate
The project is ahead of schedule
Forecast modeling based on uniform velocity decay, labor-capacity saturation, and phase-based cost rebound
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Pedagogic Games V
Quiz
•
1st Grade - Professio...
10 questions
Reforzamiento Política de Compras 09.60
Quiz
•
Professional Development
10 questions
Intro to Node.js
Quiz
•
Professional Development
10 questions
Aruga at Kalinga
Quiz
•
University - Professi...
10 questions
ASSESSMENT FOR, OF, AS LEARNING
Quiz
•
Professional Development
10 questions
Les méthodes traditionnelles de gestion de projet
Quiz
•
KG - Professional Dev...
10 questions
Stakeholder Engagement 10 soal (Chapter 13)
Quiz
•
Professional Development
10 questions
MCE EXAMINATION (COLLABORATION)
Quiz
•
Professional Development
Popular Resources on Wayground
7 questions
History of Valentine's Day
Interactive video
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
15 questions
Valentine's Day Trivia
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade