1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following represents a risk?
We have determined that our schedule is not going to meet the required deadline.
Due to a higher inflation rate, it is possible that future commodity prices will be 3 to 7% higher over the next 2 years, thus increasing the cost of the project.
There are not enough resources to complete the work on time.
The change in the prime rate has caused our funding source to be
unable to provide the money we need in the upcoming project phase.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The product owner is unavailable to decide about a product feature. What is this considered?
Work request
Impediment
Backlog refinement
Priority
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a technique used by project teams to bring everyone together on a set reoccurring basis to share what may be blocking or impeding their work or plans?
Daily standup meeting
Iteration review
Retrospective
Project kickoff
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the best example of a blocker?
The team cannot decide when to schedule the next iteration review.
The demonstration is not ready for the iteration review.
Clearance from another team to use content for the demo won’t be
ready within the current iteration.
The demonstration fails in front of the product owner during the
iteration review.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the aim of a retrospective?
To blamestorm problems
To identify who is not helping out on the team
To look back at all the work that was not completed
To identify what went well and what can be improved
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which two of the following are types of project metrics that may be appropriate for a given project? (Choose two)
Percentage of work completed
Defects
Subcontractor approvals
Process compliance
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which two of the following are objectives for running a retrospective? (Choose two)
Provide the stakeholders access to the team
Generate insights
Agree to one to two experiments to try to improve team performance
dGet feedback on the product
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
19 questions
ESL Brains - Millennials In The Workplace
Quiz
•
University - Professi...
20 questions
LHPK DAN KPDHN KC SEMARANG
Quiz
•
Professional Development
20 questions
MKT| Unidad 1 - Actividad 2 - Quizz (Bases de MKT) EXTRAXT
Quiz
•
Professional Development
19 questions
Ekonomia Społeczna
Quiz
•
Professional Development
20 questions
Business Revision
Quiz
•
Professional Development
25 questions
Taglines
Quiz
•
KG - Professional Dev...
21 questions
RATE PLANS & Features
Quiz
•
Professional Development
20 questions
Dr.S.Uma's Principles of Management Quiz
Quiz
•
University - Professi...
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade