Project Management Quiz

Project Management Quiz

Professional Development

10 Qs

quiz-placeholder

Similar activities

PM Lite draft

PM Lite draft

Professional Development

14 Qs

LL Workshop

LL Workshop

Professional Development

13 Qs

Team leading unit 302

Team leading unit 302

Professional Development

12 Qs

The quiz of Jen, based on the latest edition of OGI Focus

The quiz of Jen, based on the latest edition of OGI Focus

Professional Development

15 Qs

Communication barriers: Test your awareness

Communication barriers: Test your awareness

Professional Development

10 Qs

DVS Submission and Notation

DVS Submission and Notation

Professional Development

9 Qs

Spencers Recap Quiz

Spencers Recap Quiz

Professional Development

10 Qs

New Starter PV Quiz 2

New Starter PV Quiz 2

Professional Development

9 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

Other

Professional Development

Hard

Created by

Training Pusilkom

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While conducting procurement on a project, the project manager has received many different bids with a wide variance of estimated cost for the work. What can the project manager use to best determine which vendor has given a realistic price?

Weighing system

Screening system

Inspection and audits

Independent estimate

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager and team have decided to hire a contractor to complete building out the remaining section of the datacenter. They have the requirements listed in detail and would like to use a contract that would present the smallest amount of risk to the project. The project team members would like to purchase the materials themselves since there are very familiar with the work. What contract is best for this project?

Cost plus contractor fee

Cost plus project fee

Time and materials

Cost plus fixed fee

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The sponsor makes it clear that he does not want any of the team members to be overworked while working on a project. This means that no team member is allowed to work overtime. The sponsor is okay with the project being delayed due to this. What technique can the project manager best implement to ensure that no team member is overworked?

Lag

Resource leveling

Resource smoothing

Free float

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A large development company has just initiated a project to build a 60-story building. The project will take approximately 3 years to complete with a cost of $550 million. The development company has started to facilitate funding for the project by asking private equity firms and banks. What tools does this best represent?

Financing

Funding limit reconciliation

Analogous estimates

Parametric estimates

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager, Mark, overheard that the project team is not satisfied with the way the budget was created. They strongly believe the project will be over budget at the end. What is the next best step for Mark?

Do nothing, because the team didn't speak to Mark about it

Review how the budget was created

Bring the team together and attempt to understand why they feel this way

Ask the sponsor for approval to increase the budget

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager has been informed that the company's senior management would like a meeting about the status of the project. What should the project manager take to display the current schedule of the project?

Gantt chart

Milestone chart

WBS

Network diagram

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is currently working with the team to complete the office redesign project when a sponsor tells him to finish it 2 weeks sooner than planned. The project manager will need 4 new people to join the team to complete the work by the new deadline. What technique is best described in this scenario?

Critical path method

Schedule variance

Fast tracking

Crashing

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?