Project Time Management Quiz
Authored by Sylvie Ha
Professional Development
Professional Development
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Project schedules grow out of the basic documents that initiate a project. State true or false.
Not mentioned
Not mentioned
False
True
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
____ involves doing activities in parallel that you would normally do in sequence.
Crashing
Fast tracking
Expediting
Crushing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
Total slack
Free float
Free slack
Total time
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Project managers often illustrate progress with a(n) ____ showing key deliverables and activities.
Tracking Gantt chart
PERT chart
Gantt chart
Network diagram
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
____ dependencies involve relationships between project and non-project activities.
Mandatory
Discretionary
External
Internal
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
____ is a network diagramming technique used to predict total project duration.
Gantt charts
Critical path analysis
Critical chain scheduling
Critical chain scheduling
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The critical path always includes the most critical activities. True or false.
True
False
Not mentioned
Not mentioned
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?