
Networks and Critical Path Analysis

Quiz
•
Business
•
12th Grade
•
Hard
nyaradzo matava
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of critical path analysis in project management?
To determine the cost of each task in a project
To assign resources to tasks based on priority
To track the progress of a project using Gantt charts
To identify the longest sequence of dependent tasks and determine the shortest time needed to complete a project.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Explain the concept of Early Start Time (EST) in critical path analysis.
EST is determined by the weather conditions during the project
The Early Start Time (EST) is calculated by taking the maximum Early Finish Time (EFT) of all immediate predecessor tasks.
EST is calculated by adding the duration of all tasks in the project
The Early Start Time (EST) is the average time taken for a task to start
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is Late Finish Time (LFT) calculated in critical path analysis?
LFT = LST * Duration
LFT = LST - Duration
LFT = LST + Duration
LFT = LST / Duration
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Define Total Float in the context of critical path analysis.
Total Float is the amount of time a task must be completed.
Total Float is the total duration of a project.
Total Float is the amount of time that a task can be delayed without delaying the project completion date.
Total Float is the earliest start time of an activity.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is Free Float and how is it different from Total Float in critical path analysis?
Free Float is the time an activity can be delayed without affecting its successor, while Total Float is the time an activity can be delayed without affecting the project.
Free Float is the time an activity can be delayed without delaying the project, while Total Float is the time an activity can be delayed without delaying its successor.
Free Float is the time an activity can be delayed without delaying its successor, while Total Float is the time an activity can be delayed without delaying the project.
Free Float is the time an activity can be delayed without affecting the project, while Total Float is the time an activity can be delayed without affecting its successor.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is it important for businesses to perform critical path analysis?
To confuse stakeholders and team members
To complicate project management
To increase costs and waste resources
To identify crucial tasks, allocate resources efficiently, minimize delays, and ensure timely project completion.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Calculate the Total Float for a task with EST of 5 days, LFT of 10 days, and duration of 3 days.
4 days
6 days
1 day
2 days
Create a free account and access millions of resources
Similar Resources on Wayground
9 questions
Lean Canvas Business Model

Quiz
•
9th - 12th Grade
11 questions
Entrepreneurship I - 5.03 Vocabulary Quiz

Quiz
•
9th - 12th Grade
15 questions
Entrepreneurship Unit 5

Quiz
•
9th - 12th Grade
15 questions
manprin

Quiz
•
12th Grade
10 questions
Financial Management

Quiz
•
12th Grade
10 questions
10. Managing Strategic Change

Quiz
•
11th - 12th Grade
15 questions
Edexcel Bus: 3.3.4 Critical Path Analysis (CPA)

Quiz
•
12th Grade
10 questions
IB Business Management MCQ QuizIB_Business_Management_Gantt char

Quiz
•
12th Grade
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade