Networks and Critical Path Analysis

Networks and Critical Path Analysis

12th Grade

10 Qs

quiz-placeholder

Similar activities

manprin

manprin

12th Grade

15 Qs

10. Managing Strategic Change

10. Managing Strategic Change

11th - 12th Grade

10 Qs

Edexcel Bus: 3.3.4 Critical Path Analysis (CPA)

Edexcel Bus: 3.3.4 Critical Path Analysis (CPA)

12th Grade

15 Qs

IB Business Management MCQ QuizIB_Business_Management_Gantt char

IB Business Management MCQ QuizIB_Business_Management_Gantt char

12th Grade

10 Qs

Lean Canvas Business Model

Lean Canvas Business Model

9th - 12th Grade

9 Qs

Entrepreneurship I - 5.03 Vocabulary Quiz

Entrepreneurship I - 5.03 Vocabulary Quiz

9th - 12th Grade

11 Qs

APQP

APQP

1st Grade - Professional Development

10 Qs

Entrepreneurship Unit 5

Entrepreneurship Unit 5

9th - 12th Grade

15 Qs

Networks and Critical Path Analysis

Networks and Critical Path Analysis

Assessment

Quiz

Business

12th Grade

Hard

Created by

nyaradzo matava

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of critical path analysis in project management?

To determine the cost of each task in a project

To assign resources to tasks based on priority

To track the progress of a project using Gantt charts

To identify the longest sequence of dependent tasks and determine the shortest time needed to complete a project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Explain the concept of Early Start Time (EST) in critical path analysis.

EST is determined by the weather conditions during the project

The Early Start Time (EST) is calculated by taking the maximum Early Finish Time (EFT) of all immediate predecessor tasks.

EST is calculated by adding the duration of all tasks in the project

The Early Start Time (EST) is the average time taken for a task to start

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is Late Finish Time (LFT) calculated in critical path analysis?

LFT = LST * Duration

LFT = LST - Duration

LFT = LST + Duration

LFT = LST / Duration

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Define Total Float in the context of critical path analysis.

Total Float is the amount of time a task must be completed.

Total Float is the total duration of a project.

Total Float is the amount of time that a task can be delayed without delaying the project completion date.

Total Float is the earliest start time of an activity.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Free Float and how is it different from Total Float in critical path analysis?

Free Float is the time an activity can be delayed without affecting its successor, while Total Float is the time an activity can be delayed without affecting the project.

Free Float is the time an activity can be delayed without delaying the project, while Total Float is the time an activity can be delayed without delaying its successor.

Free Float is the time an activity can be delayed without delaying its successor, while Total Float is the time an activity can be delayed without delaying the project.

Free Float is the time an activity can be delayed without affecting the project, while Total Float is the time an activity can be delayed without affecting its successor.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important for businesses to perform critical path analysis?

To confuse stakeholders and team members

To complicate project management

To increase costs and waste resources

To identify crucial tasks, allocate resources efficiently, minimize delays, and ensure timely project completion.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Calculate the Total Float for a task with EST of 5 days, LFT of 10 days, and duration of 3 days.

4 days

6 days

1 day

2 days

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?