What is the purpose of critical path analysis in project management?

Networks and Critical Path Analysis

Quiz
•
Business
•
12th Grade
•
Hard
nyaradzo matava
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To determine the cost of each task in a project
To assign resources to tasks based on priority
To track the progress of a project using Gantt charts
To identify the longest sequence of dependent tasks and determine the shortest time needed to complete a project.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Explain the concept of Early Start Time (EST) in critical path analysis.
EST is determined by the weather conditions during the project
The Early Start Time (EST) is calculated by taking the maximum Early Finish Time (EFT) of all immediate predecessor tasks.
EST is calculated by adding the duration of all tasks in the project
The Early Start Time (EST) is the average time taken for a task to start
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is Late Finish Time (LFT) calculated in critical path analysis?
LFT = LST * Duration
LFT = LST - Duration
LFT = LST + Duration
LFT = LST / Duration
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Define Total Float in the context of critical path analysis.
Total Float is the amount of time a task must be completed.
Total Float is the total duration of a project.
Total Float is the amount of time that a task can be delayed without delaying the project completion date.
Total Float is the earliest start time of an activity.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is Free Float and how is it different from Total Float in critical path analysis?
Free Float is the time an activity can be delayed without affecting its successor, while Total Float is the time an activity can be delayed without affecting the project.
Free Float is the time an activity can be delayed without delaying the project, while Total Float is the time an activity can be delayed without delaying its successor.
Free Float is the time an activity can be delayed without delaying its successor, while Total Float is the time an activity can be delayed without delaying the project.
Free Float is the time an activity can be delayed without affecting the project, while Total Float is the time an activity can be delayed without affecting its successor.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is it important for businesses to perform critical path analysis?
To confuse stakeholders and team members
To complicate project management
To increase costs and waste resources
To identify crucial tasks, allocate resources efficiently, minimize delays, and ensure timely project completion.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Calculate the Total Float for a task with EST of 5 days, LFT of 10 days, and duration of 3 days.
4 days
6 days
1 day
2 days
Create a free account and access millions of resources
Similar Resources on Quizizz
14 questions
MCQ revision test 5

Quiz
•
12th Grade - University
15 questions
PM 1 1.02 Quizizz

Quiz
•
9th - 12th Grade
12 questions
Internal/External Communication

Quiz
•
9th - 12th Grade
12 questions
Worksheet 5: Project management tools and approaches (learner)

Quiz
•
12th Grade
8 questions
15 - Critical Path Analysis & Gantt Charts

Quiz
•
12th Grade
13 questions
Critical Path Analysis

Quiz
•
12th Grade
15 questions
Business Decision-Making Tools Quiz

Quiz
•
12th Grade
11 questions
2.01 Project management 1

Quiz
•
9th - 12th Grade
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade