1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Identify the longest task?
Fill Kettle
Boil Kettle
Put tea in cup
Put sugar in cup
Get milk out of fridge
2.
FILL IN THE BLANKS QUESTION
1 min • 1 pt
How many milestones are there?
(a)
3.
FILL IN THE BLANKS QUESTION
1 min • 1 pt
How many tasks are dependent on pouring water into a cup?
(a)
4.
FILL IN THE BLANKS QUESTION
1 min • 1 pt
How many seconds form the critical path?
(a)
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is Critical Path Analysis
A project management technique for process planning that defines critical (milestones) and non-critical tasks
A graphical display of project activities represented by an area of land showing physical features
A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site
A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does PERT stand for?
Project Evaluation and Review Technique
Programme Estimate and Reward Time
Process End and Replace Technique
Programmer Expire and Revised Timescale
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What type of diagram is this?
PERT
Dataflow diagram
Bar Chart
Gantt Chart
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?