15 - Critical Path Analysis & Gantt Charts

15 - Critical Path Analysis & Gantt Charts

12th Grade

8 Qs

quiz-placeholder

Similar activities

EXIT TICKET

EXIT TICKET

12th Grade

10 Qs

Critical Thinking Quiz

Critical Thinking Quiz

4th Grade - University

9 Qs

G12 - W5

G12 - W5

12th Grade

11 Qs

Toon Boom Storyboard Pro TOP MENU

Toon Boom Storyboard Pro TOP MENU

9th - 12th Grade

12 Qs

Hard Skills and Soft Skills

Hard Skills and Soft Skills

12th Grade

12 Qs

Windows Updates

Windows Updates

9th Grade - Professional Development

8 Qs

Esports Job Skills Quiz

Esports Job Skills Quiz

12th Grade

10 Qs

Operation Stratgey

Operation Stratgey

12th Grade

10 Qs

15 - Critical Path Analysis & Gantt Charts

15 - Critical Path Analysis & Gantt Charts

Assessment

Quiz

Computers, Business

12th Grade

Medium

Created by

Laura Sherrington

Used 115+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Identify the longest task?

Fill Kettle

Boil Kettle

Put tea in cup

Put sugar in cup

Get milk out of fridge

2.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Media Image

How many milestones are there?

3.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Media Image

How many tasks are dependent on pouring water into a cup?

4.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Media Image

How many seconds form the critical path?

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Critical Path Analysis

A project management technique for process planning that defines critical (milestones) and non-critical tasks

A graphical display of project activities represented by an area of land showing physical features

A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site

A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does PERT stand for?

Project Evaluation and Review Technique

Programme Estimate and Reward Time

Process End and Replace Technique

Programmer Expire and Revised Timescale

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

What type of diagram is this?

PERT

Dataflow diagram

Bar Chart

Gantt Chart

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

How long does it take to complete task F?

1 Month

3 Months

6 Months

8 Months