CAPM - Day 4

CAPM - Day 4

Professional Development

6 Qs

quiz-placeholder

Similar activities

Magnet Group Website Quiz

Magnet Group Website Quiz

Professional Development

8 Qs

Group Session 1 - End of Session Assessment

Group Session 1 - End of Session Assessment

Professional Development

10 Qs

Latihan Kawalan Logistik dan Pengedaran

Latihan Kawalan Logistik dan Pengedaran

Professional Development

10 Qs

Chapter 1 Introduction

Chapter 1 Introduction

University - Professional Development

10 Qs

Eni Academy - CCUS & Forestry

Eni Academy - CCUS & Forestry

Professional Development

6 Qs

Project Management - Pertamina

Project Management - Pertamina

Professional Development

10 Qs

CEK STRUCTURE

CEK STRUCTURE

Professional Development

10 Qs

Social media presentation

Social media presentation

Professional Development

8 Qs

CAPM - Day 4

CAPM - Day 4

Assessment

Quiz

Business

Professional Development

Medium

Created by

Ahmed Abdessalem

Used 1+ times

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Is the following statement true or false? The Agile Manifesto states, “We value individuals and interaction over process and tools?”

True

False

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which three of the following is not a financial-based benefit measure method?

Net present value

Internal rate of return

Return of investment

NPS

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is a financial tool that calculates the present value of all cash outflows minus the present value of all cash inflows?

Internal rate of return

Net present value

Benefit cost value

Return on investment

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Is the following statement true or false? Predictive projects are plan driven, while adaptive projects focus on team collaboration with stakeholders or customers to determine the project need by writing user stories and hybrid projects can combine or switch predictive or adaptive approaches as necessary.

True

False

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which is the best elicitation technique to use when your project team wants to facilitate a discussion with a certain set of users to get a better understanding on how they might use your project’s product?

Document analysis

Focus group

Benchmarking

Plurality

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A project team is reviewing the requirements documentation that they are responsible for working on. Which project artifact can they reference to see the connection between the requirements and the business and project objectives?

Requirements traceability matrix

RACI chart

Project charter

Scope management plan