1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your agile team working on some project which a lot of things are unknownat this moment. Hence your team decided to use "rolling wave" planning approach. Which statement are true regarding this?
It is an incremental planning in which work in near terms is planned in detailed
It is an iterative planning in which work in near terms is planned in detailed
It is an iterative planning in which work in near terms is planned in high level
It is an incremental planning in which work in near terms is planned in high level
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Due to restructing in client team, there are some changes in personnel as some new members joined your client team. As agile leader, what is your approach to ensure project participation from these new stakeholders now?
Send these new stakeholders the current status of project over an email so that they are aware of the project details
Invite these new stakeholders to planning, retrospective & review meetings
Share the project charter, team charter with the new stakeholders to make them aware of projects and teams
Share the project repository which contains all the project info with new stakeholders
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The law of diminishing marginal returns is applicable to which type of following features?
Must have
Should have
Exciters
Delighters
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
"Customer collaboration over contract negotiation" is one of Agile Manifesto. Which of the following agile approaches helps in achieving this value?
Backlog preparation
Daily Standup
Backlog refinement
Agile measurements
Answer explanation
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Team periodically demostrate the working product to product owner and stakeholders. In flow-based agile, when this demostration conducted?
At the end of iterations
At the end of projects
during retrospective
when enough features are accumulated into a set that is coherent
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which is not recomended practice when splitting large user stories in order to fit an iteration?
Splitting a large story into its constituent tasks
Splitting a large story into smaller stories if the priorities of the smaller stories are different
Splitting stories by separating functional and non functional aspects
Splitting a large story along the boundaries of the data supported by the story
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Agile team has completed 120 features so far and the project SPI is 1.2. What is the number of planned features the team should was supposed to complete?
144
120
100
the figures can not be computed with given data
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
18 questions
Change Management & Project Management PELINDO
Quiz
•
Professional Development
16 questions
P&T India Quiz - Final
Quiz
•
Professional Development
20 questions
Pedagogik
Quiz
•
Professional Development
17 questions
Leader in Me
Quiz
•
Professional Development
20 questions
Microsoft Excel
Quiz
•
KG - Professional Dev...
20 questions
LATIHAN SOAL 5 UP PPG PAUD 2021
Quiz
•
Professional Development
21 questions
Class 7 review
Quiz
•
Professional Development
20 questions
AWS Most Popular Services
Quiz
•
Professional Development
Popular Resources on Wayground
8 questions
Spartan Way - Classroom Responsible
Quiz
•
9th - 12th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
14 questions
Boundaries & Healthy Relationships
Lesson
•
6th - 8th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
3 questions
Integrity and Your Health
Lesson
•
6th - 8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
9 questions
FOREST Perception
Lesson
•
KG
20 questions
Main Idea and Details
Quiz
•
5th Grade
Discover more resources for Professional Development
15 questions
LOTE_SPN2 5WEEK3 Day 2 Itinerary
Quiz
•
Professional Development
6 questions
Copy of G5_U6_L5_22-23
Lesson
•
KG - Professional Dev...
10 questions
March Quiz
Quiz
•
Professional Development
5 questions
Copy of G5_U6_L8_22-23
Lesson
•
KG - Professional Dev...
10 questions
suffixes FUL OR LESS
Quiz
•
Professional Development