A ___ is a hierarchically structured system of tasks that represent the workflow of a construction project in increasing levels of detail.
project detail
construction contract
work breakdown structure
workflow process
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Project ___ is a description of a project being built, the major tasks and their deliverables, and any milestones, deadlines, or exclusions.
scope
contract
detail
orientation
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The advantage of the bottom-up approach to developing a schedule is that ___.
it is short and concise
it avoids scope gaps
smaller activities can be left out
individual tasks can be laid out quickly from start to finish
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
One advantage of the ___ approach is that it helps to divide complex projects into different areas of work that can then be broken down into detail.
bottom-up
top-down
historical
phased
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
At the highest level of a work breakdown structure is the ___.
project itself
activity
project phase
work package
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A(n) ___ is the lowest level in a work breakdown structure and has a grouping of tasks below it.
substructure
activity
construction phase
work package
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An activity is usually ___ days or less in duration and encompasses a single subcontractor, individual, or resource.
3
7
10
15
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?