CMA 490 - Chapter 2 Review

CMA 490 - Chapter 2 Review

University

18 Qs

quiz-placeholder

Similar activities

PROFESSIONAL PRACTICE 3 - MODULE 1 (ARCHITECTURAL FIRM)

PROFESSIONAL PRACTICE 3 - MODULE 1 (ARCHITECTURAL FIRM)

University

15 Qs

TOA_part 2

TOA_part 2

University

20 Qs

CT10_11_Structural Principles 01

CT10_11_Structural Principles 01

University

15 Qs

P231_Residential Planning and Development

P231_Residential Planning and Development

University - Professional Development

20 Qs

11/4/24

11/4/24

8th Grade - University

20 Qs

Understanding Roof Systems and Framing Hardware

Understanding Roof Systems and Framing Hardware

University

19 Qs

RA 9266

RA 9266

University - Professional Development

19 Qs

Week3_Q1_Time Terms in Construction Project

Week3_Q1_Time Terms in Construction Project

University

15 Qs

CMA 490 - Chapter 2 Review

CMA 490 - Chapter 2 Review

Assessment

Quiz

Architecture

University

Medium

Created by

Jeremiah Arnett

Used 46+ times

FREE Resource

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ___ is a hierarchically structured system of tasks that represent the workflow of a construction project in increasing levels of detail.

project detail

construction contract

work breakdown structure

workflow process

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project ___ is a description of a project being built, the major tasks and their deliverables, and any milestones, deadlines, or exclusions.

scope

contract

detail

orientation

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The advantage of the bottom-up approach to developing a schedule is that ___.

it is short and concise

it avoids scope gaps

smaller activities can be left out

individual tasks can be laid out quickly from start to finish

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One advantage of the ___ approach is that it helps to divide complex projects into different areas of work that can then be broken down into detail.

bottom-up

top-down

historical

phased

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

At the highest level of a work breakdown structure is the ___.

project itself

activity

project phase

work package

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A(n) ___ is the lowest level in a work breakdown structure and has a grouping of tasks below it.

substructure

activity

construction phase

work package

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An activity is usually ___ days or less in duration and encompasses a single subcontractor, individual, or resource.

3

7

10

15

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?