Project Management final quiz

Project Management final quiz

University

21 Qs

quiz-placeholder

Similar activities

T1 Online Business

T1 Online Business

University

20 Qs

Units 1 and 2 REVIEW

Units 1 and 2 REVIEW

University

18 Qs

Social Night - Swiss School of Management

Social Night - Swiss School of Management

6th Grade - University

20 Qs

Seminar 1-2

Seminar 1-2

University

20 Qs

The Project Management Process Groups

The Project Management Process Groups

University

21 Qs

Project Management and Balance Scorecard

Project Management and Balance Scorecard

University

16 Qs

IB Business Management - 2.2 Changes in Org Structures (HL )

IB Business Management - 2.2 Changes in Org Structures (HL )

9th Grade - University

20 Qs

Finding Neo

Finding Neo

University

25 Qs

Project Management final quiz

Project Management final quiz

Assessment

Quiz

Business

University

Hard

Created by

Anu Laukkala

Used 5+ times

FREE Resource

21 questions

Show all answers

1.

FILL IN THE BLANK QUESTION

2 mins • 1 pt

What are the three project constraints (objectives)? (type with small letters only) Time, cost and ?

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are project milestones?

Zero duration tasks

Client presentations

Project team meetings

Risk management planning

3.

FILL IN THE BLANK QUESTION

1 min • 1 pt

WBS stands for (small letters only)

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Define critical path?

The shortest path between the project start and finish

The longest path between the project start and finish

A listing of the most critical (important) activities in the project

Tasks in the project that have only a few days of slack

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When you want to do a project faster than planned and outsource some of the tasks to an external company to be done simultaneously, instead of the original plan; one after another,

Fast tracking

Project crashing

Scope re-definition

Budget reduction

6.

FILL IN THE BLANK QUESTION

1 min • 1 pt

1.    Earned value management: Your project has a budget of

10 000 chf and it is planned to last for 10 months. 4 months later, you notice you have spent 8 000chf and have finished 40% of the work. What is the earned value (EV)?

7.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Earned value management: Your project has a budget of 10 000 chf and it is planned to last for 10 months. 4 months later, you notice you have spent 8 000chf and have finished 40% of the work. What is the actual cost (AC)?

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?