Project Process Group and the Project Charter

Project Process Group and the Project Charter

10th Grade

10 Qs

quiz-placeholder

Similar activities

Jobs Vocabulary

Jobs Vocabulary

6th - 10th Grade

10 Qs

The Quiz Where Everything Is Wrong

The Quiz Where Everything Is Wrong

KG - University

10 Qs

Costa's Levels of Questioning

Costa's Levels of Questioning

6th Grade - University

15 Qs

Forms and Documents

Forms and Documents

9th - 12th Grade

6 Qs

TOEFL Structure (Skills 46-48)

TOEFL Structure (Skills 46-48)

9th Grade - Professional Development

10 Qs

Project management and Execution

Project management and Execution

1st Grade - Professional Development

10 Qs

Project Management - Mid Unit

Project Management - Mid Unit

9th - 12th Grade

10 Qs

Workplace Readiness Skills (B)

Workplace Readiness Skills (B)

9th - 12th Grade

10 Qs

Project Process Group and the Project Charter

Project Process Group and the Project Charter

Assessment

Quiz

Professional Development

10th Grade

Hard

Created by

Unit Komputer

Used 17+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The initiating process includes which task?

Assigning work to project team members

Sequencing project activities

Approving a project and authorizing work to begin

Coordinating resources to complete the project work

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

This person is responsible for authorizing the project to begin and signing the project charter.

Project sponsor

Executive in the organization who requested the project

Project champion

Project manager

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Beginning one phase of a project before another has finished is example of what?

Sequencing

Compression

Fast tracking

Constricting

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A primary role of a project manager includes informing this person of changes, status, conflicts, and issues on the project.

The project requestor

the project sponsor

The project champion

The most influential project stakeholder

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following is not a component of a high-level requirements document or product description?

Historical data

Problem statement

Technical requirements

Testing scenarios

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which stakeholder assigns employees to the project?

Project manager

Functional manager

Customer

Sponsor

7.

MULTIPLE SELECT QUESTION

2 mins • 1 pt

Which three of the following options are process groups in the project management process groups?

Planning

Initiating

Monitoring and controlling

Procurement

Scope

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Professional Development