Which of the following must hold for an activity on the critical path in a PERT network?

a) Slack = 0

a) ES=LS

a) EF=LF

a) All of these

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project can have more than one critical path.

True

False

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A critical path must go from “start” node to “finish” node

True

False

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The performance times (durations) of the “start” node and “finish” node are

0

To be determined by manager

Usually different, but at least 1 working day

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

One day delay of a task on the critical path would cause one day delay of the whole project

True

False

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

We should go ___________ when calculating latest times, LS and LF

Forward

Backward

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Suppose activity H’s immediate predecessors are D and G. EF=8 for G. What is ES for H?

8

10

12

Not enough information is provided in here

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?