CPM Network Diagram Concepts

CPM Network Diagram Concepts

Assessment

Interactive Video

Other

9th - 10th Grade

Hard

Created by

Thomas White

FREE Resource

The video tutorial explains how to draw CPM Network diagrams by hand, using two examples. The first example demonstrates creating a diagram with minimal dummy activities, ensuring correct predecessor relationships. The second example addresses the challenge of multiple start nodes, showing how to consolidate nodes to minimize dummy activities. The tutorial emphasizes numbering nodes so arrows point from lower to higher numbers, ensuring correct diagram structure.

Read more

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main focus of the video tutorial?

Drawing CPM Network diagrams by hand

Learning about project management software

Exploring Agile methodologies

Understanding Gantt charts

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in drawing the CPM Network diagram for the first project?

Drawing activity A

Drawing activity B

Drawing activity C

Drawing activity D

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which activities depend on activity A in the first project?

Activities F and G

Activities B and C

Activities D and E

Activities H and I

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a dummy activity in a CPM Network diagram?

To show dependency without time or duration

To mark the end of a project

To indicate the start of a project

To represent an actual task with duration

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can the number of dummy activities be minimized in a CPM Network diagram?

By removing dependencies

By combining activities

By adding more nodes

By redrawing the diagram

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the final step in completing the first example of the CPM Network diagram?

Adding more dummy activities

Numbering each node

Removing all arrows

Starting a new project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a limitation of the CPM Network diagram mentioned in the second example?

It can only start on one node and end on one node

It requires multiple dummy activities

It cannot represent dependencies

It is only suitable for small projects

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?