PMI-RMP Certification Training - Case Study 5
Interactive Video
•
Information Technology (IT), Architecture
•
University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How many days and resources were initially estimated for the project activity?
Ten days with one resource
Two days with five resources
Five days with two resources
Three days with three resources
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What did the team realize about the project activity during its course?
It needed additional training for the team
It could not be completed within the estimated time
It required more resources than initially planned
It could be done in less than two hours with a software purchase
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the cost of the software license that could expedite the project activity?
$50
$150
$200
$100
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should the project manager do upon discovering the software solution?
Evaluate the cost-benefit of purchasing the software
Delay the project to find a better solution
Hire more resources to speed up the process
Ignore the software and stick to the original plan
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How many man-days could potentially be saved by purchasing the software?
5 man-days
10 man-days
15 man-days
20 man-days
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?