Microsoft Project 2021 From Beginners to Advanced - Set and Clear a Baseline

Microsoft Project 2021 From Beginners to Advanced - Set and Clear a Baseline

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the concept of baselines in project management, detailing how to set, view, and manage baselines to track project progress. It covers the importance of baselines in comparing planned versus actual project data, and demonstrates how to handle scheduling conflicts. The tutorial also shows how to manage multiple baselines and clear them when necessary.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should you do if you encounter a scheduling conflict when opening course files?

Close the file and try again later.

Restart the planning wizard.

Click on 'Continue' to allow the conflict.

Contact the course instructor.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a component of a baseline?

Durations

Start and finish dates

Cost estimates

Task dependencies

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many baselines can you set in total for a project?

11

8

5

15

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in setting a baseline for a project?

Clear all previous baselines.

Open the Gantt chart.

Navigate to the project tab and schedule group.

Contact the project manager.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What information is displayed in the variance table?

Only the baseline start and finish dates

Only the project cost estimates

Both actual and baseline start and finish dates

Only the actual start and finish dates

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you view different baselines in the Gantt chart?

By clearing all existing baselines

By opening a new project file

By adjusting the project timeline

By selecting the baseline from the dropdown in the bars styles group

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should you do if a baseline is no longer relevant?

Contact the project manager for advice

Clear the baseline using the clear baseline option

Ignore it and continue with the project

Set a new baseline over it