Planning and Control Using Microsoft Project 365 and 2021 - Workshop 17 - Resource Graphs and Tables

Planning and Control Using Microsoft Project 365 and 2021 - Workshop 17 - Resource Graphs and Tables

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial covers resource levelling in Microsoft Project. It begins with an introduction to the project and the importance of resource levelling. The tutorial then demonstrates how to identify overallocated resources using resource graphs. It explains setting baselines and using Gantt charts to track project delays. The video provides a detailed guide on manual resource levelling, including setting options and saving schedules. Finally, it explores advanced levelling options, such as allowing splits and selecting by ID, to manage project timelines effectively.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of using resource graphs in project management?

To assign tasks to team members

To identify over-allocated resources

To calculate project costs

To visualize project timelines

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does setting a baseline in a project help you to achieve?

It allows for the comparison of planned and actual progress

It helps in tracking project costs

It automatically assigns resources

It generates project reports

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the significance of negative float in a project schedule?

It represents the total project cost

It indicates a surplus of resources

It shows that the project is ahead of schedule

It highlights delays in the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which option allows for splitting activities during resource levelling?

Standard levelling

Manual levelling

Allowing slits

Selecting by ID

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens when you clear levelling in a project schedule?

New tasks are automatically added

The project timeline is extended

All resource allocations are removed

The project returns to its original state