Project Management Quiz
Authored by Poornima H N
Other
University
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
25 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
What is the primary objective of project management?
To complete the project within budget and time
To ensure quality deliverables only
To satisfy stakeholders only
To reduce team size
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following is NOT a project constraint?
Scope
Time
Cost
Marketing
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which project management process involves defining and controlling what is and is not included in the project?
Scope Management
Time Management
Cost Management
Quality Management
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
PERT is used for:
Scheduling and controlling
Budget estimation
Communication planning
Risk analysis
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
In CPM, the activity with zero float is called:
Non-critical activity
Critical activity
Float activity
Dummy activity
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which document officially starts a project?
Project charter
Project schedule
Risk register
Work breakdown structure
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Who is responsible for the overall success of a project?
Client
Project sponsor
Project manager
Team member
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?