50 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the first step in defining project work?
Develop WBS
Define Scope
Develop Project Management Plan
Collect Requirements
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does the WBS stand for?
Work Breakdown Structure
Workflow Breakdown Schedule
Work Budget Structure
Workflow Baseline Summary
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the main goal of the 'Define Scope' process?
Develop estimates
List tasks
Describe deliverables and boundaries
Assign roles
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What technique is used to analyze root causes of major issues?
SWOT analysis
WBS
Fishbone Diagram
PERT
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which tool is used to identify the logical order of activities?
RACI matrix
Critical Chain Method
WBS
Network Diagram
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which performance index is used to measure schedule efficiency?
CPI
SV
SPI
EAC
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does SPI stand for?
Schedule Priority Indicator
Schedule Performance Index
System Project Indicator
Schedule Planning Increment
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?