Quiz Lesson 3 - Topic D (Resources and Procurement)

Quiz
•
Professional Development
•
Professional Development
•
Medium
Abdul Habib Aulfat
Used 4+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of the RACI chart in resource management?
To define procurement phases for acquiring resources
To allocate budget resources to specific tasks
To clarify roles and responsibilities for project activities
To determine competency gaps in the project team
Answer explanation
The primary purpose of the RACI chart is to clarify roles and responsibilities for project activities, ensuring that everyone understands their specific contributions and accountability within the project.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What document describes how goods and services will be procured in a project?
Statement of Work (SOW)
Procurement Management Plan
Resource Management Plan
Request for Proposal (RFP)
Answer explanation
The Procurement Management Plan outlines how goods and services will be acquired for a project, detailing procurement processes, roles, and responsibilities, making it the correct choice.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which procurement document is used to gather basic information about potential sellers?
Invitation for Bid (IFB)
Request for Information (RFI)
Request for Proposal (RFP)
Request for Quotation (RFQ)
Answer explanation
The Request for Information (RFI) is specifically designed to gather basic information about potential sellers, helping organizations understand the market and capabilities before proceeding with further procurement steps.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following best describes a cost-plus-fixed-fee (CPFF) contract?
The seller is paid a fixed amount regardless of project costs.
The seller is reimbursed for actual costs plus a fixed fee.
The seller is paid a fixed price with incentives for performance.
The seller is reimbursed for costs and awarded an additional fee for exceptional work.
Answer explanation
A cost-plus-fixed-fee (CPFF) contract means the seller is reimbursed for actual costs incurred plus a fixed fee for their services, making the second option the correct description.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In adaptive teams, why are team members encouraged to be T-shaped?
It ensures every team member has deep expertise in one area.
It allows team members to take on both specialist and generalist roles.
It enforces strict hierarchy and responsibilities in the team.
It ensures every team member works only on their primary responsibility.
Answer explanation
In adaptive teams, being T-shaped means team members can specialize in one area while also having the flexibility to contribute in other areas. This versatility enhances collaboration and problem-solving.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of a resource calendar in project management?
To track project deliverables and timelines
To identify the working days and availability of resources
To allocate financial resources to specific activities
To document team roles and responsibilities
Answer explanation
The resource calendar is essential for identifying the working days and availability of resources, ensuring effective scheduling and resource allocation throughout the project.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a key difference in resource management between predictive and adaptive approaches?
Adaptive approaches use hierarchical teams, while predictive does not.
Predictive approaches assign resources based on detailed upfront planning, while adaptive teams self-organize to distribute work.
Predictive approaches rely solely on generalists, while adaptive approaches use specialists.
Adaptive teams follow strict resource allocation plans.
Answer explanation
The key difference is that predictive approaches rely on detailed upfront planning for resource allocation, while adaptive teams self-organize, allowing for more flexibility in distributing work.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
QUIZ NEOP

Quiz
•
Professional Development
10 questions
Mentoring & Coaching Pert 7 Quality and Procurement - PreTest

Quiz
•
Professional Development
10 questions
PDRI (Project Definition Rating Index) - Assignment

Quiz
•
Professional Development
10 questions
Procurement 10 soal (Chapter 12)

Quiz
•
Professional Development
12 questions
Procurement and terms related_Week1_T3

Quiz
•
Professional Development
15 questions
RIO 2019

Quiz
•
Professional Development
5 questions
procurement process

Quiz
•
Professional Development
10 questions
Communication Skill Test

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade