MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Before the team in Uruzgan province creates the project schedule, they agree on scheduling tools, reporting frequency, and how performance will be tracked.Which process is being executed?
Define Activities
Plan Schedule Management
Control Schedule
Planning framework setup involving tool alignment, stakeholder dashboards, and scheduling baselines
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While preparing for construction in Daykundi province, the team breaks the high-level deliverable “Build clinic” into smaller tasks such as digging, plumbing, and tiling. What process are they carrying out?
Develop Schedule
Estimate Activity Durations
Define Activities
Subtask planning with task deconstruction, effort assignment, and resource pooling
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an effort to build logical task flow in Ghazni province, the coordinator arranges activities based on dependencies, ensuring proper task order and timing. Which process is being followed?
Develop Schedule
Estimate Activity Durations
Sequence Activities
Task logic alignment using relationship modeling and sequence buffering
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After receiving input from engineers in Laghman province, the project manager calculates that each solar panel installation will take four days based on historical data. Which process does this reflect?
Estimate Activity Durations
Define Activities
Control Schedule
Effort forecasting through resource review and benchmarked productivity metrics
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Using MS Project in Berlin, the team inputs task durations and dependencies, then analyzes the Gantt chart and critical path to set a realistic timeline. What process are they completing?
Develop Schedule
Control Schedule
Sequence Activities
Time modeling through logic-driven schedule creation with float and path visibility
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While reviewing actual progress against the plan in Balkh province, the manager notices that key activities are behind schedule and considers adding weekend work to catch up. What process is this?
Develop Schedule
Control Schedule
Define Activities
Reactive scheduling review using baseline comparison and corrective action evaluation
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kabul, a documentation task is allowed to start two days before coding is complete, to accelerate delivery without waiting for 100% task finish. Which scheduling technique is being used?
Lag
Crashing
Lead
Task concurrency model with forecast-based overlap and priority realignment
Similar Resources on Wayground
10 questions
CELTA Assignment 1 (FOL)

Quiz
•
Professional Development
10 questions
Didactics I - Review

Quiz
•
University - Professi...
8 questions
Quiz Lesson 2 - Topic B (Form the Team)

Quiz
•
Professional Development
10 questions
NodeJs: Cron jobs

Quiz
•
Professional Development
10 questions
Self-Regulated Learning Quiz

Quiz
•
Professional Development
10 questions
Trainees Meet-up May 2025

Quiz
•
Professional Development
8 questions
ELA Lab PD Check for Understanding

Quiz
•
Professional Development
10 questions
Growth Mindset and Proactivity Quiz

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade