Which of the following best describes a **project** according to the sources?

Project Management Quiz

Quiz
•
Instructional Technology
•
University
•
Easy
Joselin Neutro
Used 3+ times
FREE Resource
77 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An ongoing and repetitive set of activities.
A temporary and unique undertaking to achieve a specific outcome with a defined duration.
A continuous process aimed at improving existing products or services.
A set of unrelated activities managed independently.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
According to the sources, what is a significant reason why **software projects often fail**?
Too much user involvement.
Highly skilled resources.
Clear and complete requirements.
**Incomplete requirements**.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The Project Management Institute (PMI) defines Project Management as:
The use of software tools to plan and track project activities.
The process of managing teams to complete tasks on time.
**The application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements**.
Ensuring projects are completed within budget.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is highlighted as a **unique feature of Information Systems (IS) Projects**?
They always have a clearly defined and unchanging scope.
There is typically no difficulty in hiring IS personnel.
**They often face a changing technological context**.
Stakeholder involvement is generally straightforward.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a key **benefit of effective project management** according to the sources?
Increased project duration.
Guaranteed project success regardless of external factors.
**Improves the chance of project success and delivers expected benefits**.
Minimising stakeholder satisfaction.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary difference between **Projects and Operations** as described in the sources?
Operations have a defined start and end date, while projects are ongoing.
Projects aim to create repetitive outputs, while operations focus on unique outcomes.
**Projects are temporary and unique, while operations are ongoing and repetitive**.
The role of a project manager is central to both projects and operations in the same way.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main purpose of the **Project Management Institute (PMI)**?
To provide software tools for project scheduling.
To offer funding for large-scale projects.
**To be the leading professional association for project management and the authority for a global community of project professionals**.
To regulate the pricing of project management services.
Create a free account and access millions of resources
Similar Resources on Wayground
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade