CHAP9

CHAP9

University

20 Qs

quiz-placeholder

Similar activities

Questionnaire Design

Questionnaire Design

University

17 Qs

Pokemon

Pokemon

KG - University

15 Qs

QUIZ ON INDEPENDANCEDAY

QUIZ ON INDEPENDANCEDAY

KG - University

15 Qs

Youtuber facts

Youtuber facts

KG - University

18 Qs

Anong kwentong Raikan mo?

Anong kwentong Raikan mo?

KG - Professional Development

16 Qs

Batboy

Batboy

KG - University

15 Qs

Marketing and Promotion Quiz #2

Marketing and Promotion Quiz #2

University

20 Qs

journey of a river

journey of a river

KG - Professional Development

15 Qs

CHAP9

CHAP9

Assessment

Quiz

Other

University

Practice Problem

Medium

Created by

M22 M22

Used 10+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The term ordered activity means:

Tasks must either precede or follow other tasks in project planning and management.

Tasks cannot be performed unless the project manager issues a specific command to perform the work.

Prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.

Tasks are not performed unless the customer issues a specific request to perform the work.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A sequence of activities defined by the project network logic is a(n):

Event.

Path.

Node.

Route.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One of the defining points of a network, a junction point joined to some or all of the others by dependency lines, is called a(n):

Event.

Path.

Node.

Burst.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

These can be located by doing a backward pass through a network.

Critical paths

Merge activities

Successors

Burst activities

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An activity has an expected duration and an expected cost. Another name for an activity is a(n):

Work package.

Node.

Critical path.

Event.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Serial activities are those that:

Flow from one to the next in sequence.

Have sequential numbers.

Have the same numbers.

Should be performed simultaneously.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Concurrent activities are:

Activities that must be done one after the other.

Activities that can be performed at the same time.

Activities that use labor from the same group of workers.

Activities that use resources from the same resource pool.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?