CHAP9

CHAP9

University

20 Qs

quiz-placeholder

Similar activities

Chapter 1 Adaptive Environmental Management Part 1

Chapter 1 Adaptive Environmental Management Part 1

University

15 Qs

Project Management POP Quiz 1

Project Management POP Quiz 1

University

20 Qs

AGBUS 1220- QUIZ 3

AGBUS 1220- QUIZ 3

University

20 Qs

Intro to IE Recap

Intro to IE Recap

University

19 Qs

Software Engineering

Software Engineering

University

20 Qs

Energy Production During Exercise

Energy Production During Exercise

9th Grade - University

18 Qs

Setting The Stage for Positive Behavior

Setting The Stage for Positive Behavior

University

15 Qs

RHS

RHS

4th Grade - Professional Development

20 Qs

CHAP9

CHAP9

Assessment

Quiz

Other

University

Medium

Created by

M22 M22

Used 10+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The term ordered activity means:

Tasks must either precede or follow other tasks in project planning and management.

Tasks cannot be performed unless the project manager issues a specific command to perform the work.

Prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.

Tasks are not performed unless the customer issues a specific request to perform the work.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A sequence of activities defined by the project network logic is a(n):

Event.

Path.

Node.

Route.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One of the defining points of a network, a junction point joined to some or all of the others by dependency lines, is called a(n):

Event.

Path.

Node.

Burst.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

These can be located by doing a backward pass through a network.

Critical paths

Merge activities

Successors

Burst activities

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An activity has an expected duration and an expected cost. Another name for an activity is a(n):

Work package.

Node.

Critical path.

Event.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Serial activities are those that:

Flow from one to the next in sequence.

Have sequential numbers.

Have the same numbers.

Should be performed simultaneously.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Concurrent activities are:

Activities that must be done one after the other.

Activities that can be performed at the same time.

Activities that use labor from the same group of workers.

Activities that use resources from the same resource pool.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?