Project Quality Management Quiz

Project Quality Management Quiz

University

20 Qs

quiz-placeholder

Similar activities

MANU 4211|MFGA 4210: Chapter 6 & 7a

MANU 4211|MFGA 4210: Chapter 6 & 7a

University

16 Qs

The Project Management Process Groups

The Project Management Process Groups

University

21 Qs

PUE - Entrepreneurship

PUE - Entrepreneurship

University

20 Qs

Supply chain and logistics management

Supply chain and logistics management

3rd Grade - University

19 Qs

Project Management and Balance Scorecard

Project Management and Balance Scorecard

University

16 Qs

Seminar 1-2

Seminar 1-2

University

20 Qs

IGCSE Business Studies - 4.5.1 Quality Quiz

IGCSE Business Studies - 4.5.1 Quality Quiz

9th Grade - University

20 Qs

Module 4 (Lesson 1-2)

Module 4 (Lesson 1-2)

University

20 Qs

Project Quality Management Quiz

Project Quality Management Quiz

Assessment

Quiz

Business

University

Medium

Created by

Sas Pratama

Used 1+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is NOT a part of quality?

Fitness for use

Conformance to requirements

Value to the sponsor

Customer satisfaction

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A project manager is using a histogram to analyse defects found by the team during inspection activities. What process is being performed?

Plan Quality Management

Control Quality

Perform Quality Assurance

Verify Scope

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is NOT an example of cost of quality?

Having team members spend extra time reviewing requirements with the stakeholders

Paying extra programmers to help meet a deadline

Hiring extra inspectors to look for defects

Sending a crew to repair a defective product that was delivered to the client

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

You’re working with an audit team to check that your company’s projects all meet the same quality standards. What process is being performed?

Plan Quality Management

Control Quality

Perform Quality Assurance

Perform Quality Management

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

You’re managing a project to deliver 10,000 units of custom parts to a manufacturer that uses Just-in-Time management. Which of the following constraints is most important to your client?

The parts must be delivered on time.

The parts must be delivered in a specific order.

The parts must conform to ISO specifications.

The parts must be packaged separately.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is NOT part of the Quality Management plan?

Strategies for handling defects and other quality problems

Guidance on how the project team will implement the company’s quality policy

Metrics for measuring your project’s quality

A description of which deliverables don’t have to be inspected

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following tools and techniques is used to show which categories of defects are most common?

Control charts

Pareto charts

Check sheets

Flowcharts

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?