1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Hollie is managing a bathroom renovation project that has a budget of $1,500 and is 40% complete. Hollie planned to spend $500 a month on the three-month project. Hollie is evaluating the status of the project at the end of the first month. What is the project's planned value?
$500
$600
$1,000
$1,500
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project manager would like to show the rate at which the project is progressing compared to what was planned. What indicator should she reference?
Gantt chart
Schedule variance
Variance report
Schedule performance index
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Tucker is the construction project manager for a new school building. He measures the project's performance and progress by looking at the planned value, earned value, and actual cost. Which method is Tucker using to determine the project performance?
Forecasting
Performance review(s)
Cost management plan
Earned value management
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Hollie is managing a bathroom renovation project that has a budget of $1,500 and is 40% complete. She planned to spend $500 a month on the three-month project. Hollie is evaluating the status of the project at the end of the first month. What is the project's budget at completion?
$500
$600
$1,000
$1,500
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project manager would like to determine the aggregate estimated costs from the individual work packages to create a detailed breakdown of projected costs. In which process is the project manager most likely participating?
Control costs
Estimate costs
Determine budget
Earned value management
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Hollie is managing a bathroom renovation project. The project has a budget of $1,500 and is 40% complete. The project is a three-month project and Hollie planned to spend $500 a month on the project. Hollie is evaluating the status of the project at the end of the first month. What is the project's earned value?
$500
$600
$1,000
$1,500
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has a number of experts approximating the expense of completing the project's activities. This process is known as:
Determine the budget
Controlling costs
Analogous estimating
Estimating costs
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
2. Financial Institutions - Spell it!
Quiz
•
9th Grade
10 questions
Cashflow
Quiz
•
2nd - 11th Grade
10 questions
Bauran Pemasaran (Marketing Mix)
Quiz
•
7th Grade - University
13 questions
Savings Account
Quiz
•
9th - 12th Grade
17 questions
Production department and others
Quiz
•
9th - 10th Grade
10 questions
Security of People, Property & Information
Quiz
•
9th Grade
12 questions
Businesses and Inflation
Quiz
•
9th Grade
15 questions
Accounting Basics
Quiz
•
9th - 12th Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
10 questions
Probability Practice
Quiz
•
4th Grade
15 questions
Probability on Number LIne
Quiz
•
4th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
6 questions
Appropriate Chromebook Usage
Lesson
•
7th Grade
10 questions
Greek Bases tele and phon
Quiz
•
6th - 8th Grade