24-25 PM1 Charter Creation & Decision Making

24-25 PM1 Charter Creation & Decision Making

9th - 12th Grade

17 Qs

quiz-placeholder

Similar activities

project management

project management

12th Grade - University

20 Qs

PM2 Unit 4 Review (PMI)

PM2 Unit 4 Review (PMI)

9th - 12th Grade

21 Qs

2.01 - 2.03 PM Quizizz

2.01 - 2.03 PM Quizizz

9th - 12th Grade

15 Qs

PMI Mock Follow-up 1 2023

PMI Mock Follow-up 1 2023

10th Grade

20 Qs

Project Managment  1.00 vocaulary

Project Managment 1.00 vocaulary

9th - 12th Grade

20 Qs

PM1 Unit 5 Review

PM1 Unit 5 Review

9th - 12th Grade

22 Qs

Project Management Quiz

Project Management Quiz

12th Grade

15 Qs

PM2 23Spring Student Deemed Toughest PMI

PM2 23Spring Student Deemed Toughest PMI

10th Grade

22 Qs

24-25 PM1 Charter Creation & Decision Making

24-25 PM1 Charter Creation & Decision Making

Assessment

Quiz

Business

9th - 12th Grade

Hard

Created by

Bobbie Jones

Used 79+ times

FREE Resource

17 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Delores is leading a marketing project. She meets with the stakeholders to define and document all the needs for the marketing project. The activity that Delores is participating in is referred to as:

collecting requirements.

controlling the scope.

creating the WBS.

verifying the scope.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Kristi is in charge of planning a charity event for the hospital. She wants to review the requirements of each of the stakeholders. Kristi should be reviewing which document?

requirements documentation

requirements management plan

requirements traceability matrix

work breakdown structure

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Jackie is developing a document that will outline the methods to create and manage requirements, as well as the method used to prioritize requirements. Jackie is working on the:

requirements documentation.

requirements management plan.

requirements traceability matrix.

work breakdown structure.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Sam is an event planner and is considering locations for an annual conference. He has decided to ask the board of directors to vote on two locations, so that whichever location receives over 50% of the group's support will win. Sam is using which technique to collect requirements?

dictatorship

majority

plurality

unanimity

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Kacie is working on a new car design for an automotive company. She is currently working on a way to analyze, document, and manage all the stakeholder requirements for the new design. Kacie is working on the:

requirements management plan.

requirements documentation.

requirements traceability matrix.

work breakdown structure.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Carol is managing a construction project and is considering relocating her team closer to the project construction worksite. She asks the stakeholders to vote on this decision and will make the move only if they all agree to it. Carol is using which tool or technique to collect requirements?

dictatorship

majority

plurality

unanimity

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Peter is working on a respiration project for firefighters. Before finalizing the product requirements, he would like to show a working model to the firefighters at the local station to gather feedback. The technique that Peter should use to test the working model would be a/an:

facilitated workshop.

observation.

prototype.

survey.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?