To be deemed a ‘project’ your activity must have the following characteristics:

Project Management Quiz 1

Quiz
•
Education
•
University
•
Medium
Hooi Lim
Used 6+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
An official start and end date
An outcome that provides a benefit or value
Requires an allocation of resources
All of the above
Answer explanation
All of the above are key characteristics that determine what a project ‘looks like’ or what it needs to have to be called a project. Since there is a start and end date it also indicates that this is a temporary undertaking that requires you to use the allocated resources for a specific outcome or end product.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Successful project management requires you to manage each stage of your project from the start to the end:
True
False
Answer explanation
A project manager is responsible for the project throughout all of the phases of the project life cycle. They are accountable during each phase and as a result can ensure success of the project.
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
In successfully managing your project, you will need to:
Understand what is required to be delivered and by when
Plan along the way
Borrow money to cover costs
Engage with the stakeholders at the closure of the project
Answer explanation
You will need to understand what the requirements of the project are and how you might go about delivering the project within the time agreed.
Planning needs to occur before any actions are taken and should not be done ‘along the way’. The budget is predetermined during the planning phase and the money within the budget needs to be deployed carefully so that the project can be successfully managed. Stakeholders need to be communicated with throughout the life cycle of the project and not only at the end when the project ends.
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The initiation (beginning) phase requires you to:
Implement your project
Engage with stakeholders
Understand your needs and consider all possible options
Specify your project resources
Answer explanation
The initiation phase is usually the shortest phase of the project life cycle, and it is at this point where you identify what the project requires you to do and to consider all of the options to approach your project.
The project is only implemented once there is clear understanding of the project requirements and thorough planning has been undertaken. Resourcing the project and engaging with stakeholders occur later within the project management lifecycle and these can only be done successfully after initiation and planning.
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
In addition to Monitor and review which option best describes the phases of your project from start to end:
Initiation, Execution, Planning, Closure
Initiation, Planning, Execution, Closure
Planning, Execution, Initiation, Closure
Planning, Initiation, Execution, Closure
Execution, Planning, Initiation, Closure
Answer explanation
The project management life cycle follows a distinct process that needs to be followed in that order. Initiation is the first phase whereby you identify the project and consider options as to how you might approach it. You will then enter a planning phase where you take time to carefully plan your scope, schedule and costing for the project.
Once your planning is in place, you are ready to execute your project and manage risk, your team and stakeholders. The final phase of any project is ‘closure’ where your project ends, and you hand over the completed product or service to the stakeholder.
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Successful project management requires your project to:
Be delivered on time
Be delivered within the budget
Meet your project requirements
Cover all of the above
Answer explanation
Since a project is a temporary endeavor, it needs to be completed within the agreed timeframe determined, using the budget and resources allocated and meet the objectives outlined in the initiation phase of the project life cycle.
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A good project manager is deemed to have effective communication skills:
True
False
Answer explanation
A good project manager often has effective communication skills because they are usually required to engage with a team and multiple stakeholders.
Create a free account and access millions of resources
Similar Resources on Quizizz
5 questions
Project Management

Quiz
•
University
10 questions
Design Rules

Quiz
•
University
6 questions
Project Management Quiz 2

Quiz
•
University
10 questions
Project Management Basics

Quiz
•
University
10 questions
PROJECT LIFECYCLE

Quiz
•
University
10 questions
Day 3 - Quiz Review D1 & D2

Quiz
•
University
10 questions
Reviewer

Quiz
•
University
7 questions
Project Management - Quizz

Quiz
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade