1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is informed midway through project planning that she was given inaccurate data regarding new regulations affecting the required end date of her project. She may need to make a few adjustments, but she thinks she can still manage the project to complete it before the regulations take effect. She confirms this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?

Critical path method

Flowchart

Precedence diagramming

Work breakdown structure

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A design engineer is helping to ensure that the dependencies within her area of expertise are properly defined on the project. The design of several deliverables must be complete before manufacturing can begin. This is an example of what type of dependency?

Discretionary dependency

External dependency

Mandatory dependency

Scope dependency

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Your sponsor and stakeholders have made it clear they wish to be kept informed on the project status. There are many aspects of the project on which you will report, and you want to choose the most appropriate tool to use in each case. Which of the following are generally illustrated better by bar charts than network diagrams?

Logical relationships

Critical paths

Resource trade-offs

Progress or status

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A heuristic is best described as a:

Control tool

Scheduling method

Planning tool

Generally accepted rule

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Lag means:

The amount of time an activity can be delayed without delaying the project finish date

The amount of time an activity can be delayed without delaying the early start date of its successor

Waiting time

The product of a forward and backward pass

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is new to the company but has 10 years of project management experience. She is given a medium-sized project and is asked to plan so it is finished as quickly as possible because the company has a large list of projects to complete in the coming year. She will be given another project to manage as soon as she has this one baselined. She needs to report on the longest time the project will take. Which of the following is the best project management tool to use to determine this?

Work breakdown structure

Network diagram

Bar chart

Project charter

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is correct?

The critical path helps prove how long the project will take.

There can be only one critical path.

The network diagram will change every time the end date changes.

A project can never have negative float.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?