Activity-Based Costing Quiz

Activity-Based Costing Quiz

University

85 Qs

quiz-placeholder

Similar activities

social quiz

social quiz

KG - Professional Development

80 Qs

Post-Revolutionary American Government

Post-Revolutionary American Government

University

86 Qs

MID TEST FINANCIAL MANAGEMENT

MID TEST FINANCIAL MANAGEMENT

University

90 Qs

practical 4 study guide

practical 4 study guide

8th Grade - University

80 Qs

PPKN Grade 3 Final

PPKN Grade 3 Final

3rd Grade - University

89 Qs

Incarceration Nation Exam #2 Mega Review

Incarceration Nation Exam #2 Mega Review

University

81 Qs

Reconstruction Test

Reconstruction Test

6th Grade - University

83 Qs

US History Geography Quiz

US History Geography Quiz

8th Grade - University

83 Qs

Activity-Based Costing Quiz

Activity-Based Costing Quiz

Assessment

Quiz

Social Studies

University

Practice Problem

Easy

Created by

Đào Sơn

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

85 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the following statement TRUE or FALSE regarding activity-based costing? "A cost pool is an activity which consumes resources and for which overhead costs are identified and allocated"

TRUE

FALSE

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the following statement TRUE or FALSE regarding activity-based costing (ABC) and cost drivers? "A cost driver is any factor that cause a change in the cost of an activity"

TRUE

FALSE

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the following statement TRUE or FALSE regarding activity-based costing? "Life-cycle costing takes into account all costs incurred in a product like life-cycle with exception of sunk costs incurred on research and development"

TRUE

FALSE

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the following statement TRUE or FALSE regarding activity-based costing? "Life-cycle costing ensures a profit is generated over the life of the product"

TRUE

FALSE

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the following statement about target costing TRUE or FALSE ? "Products should be discontinued if there is a target cost gap"

TRUE

FALSE

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the following statement about target costing TRUE or FALSE ? "A target cost gap is the difference between the target cost for a product and its projected cost"

TRUE

FALSE

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the following statement about target costing TRUE or FALSE ? "A risk with target costing is that cost reductions may affect the perceived value of the product"

TRUE

FALSE

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?