
Project Management Plan Schedule - D2

Quiz
•
Business
•
University
•
Medium
Paolino Kitieu
Used 2+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project management plan, what is the purpose of the schedule?
To identify and mitigate project risks
To define and communicate specific, measurable, achievable, relevant, and time-bound goals and objectives
To outline the specific tasks, milestones, and deadlines for completing the project
To allocate resources and assign tasks to team members
Answer explanation
In a project management plan, the schedule is a critical component that outlines the specific tasks, milestones, and deadlines for completing the project.
It is a visual representation of the project, usually in the form of a Gantt chart or network diagram, which shows the dependencies between tasks and the critical path of the project.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following best describes the application of the critical path method (CPM)?
A tool used to identify and mitigate project risks
A method for tracking and managing project costs
A technique for identifying the sequence of project tasks that must be completed on time in order for the project to be completed on schedule
A method for allocating resources and assigning tasks to team members
Answer explanation
CPM is a project management technique used to identify the sequence of project tasks that must be completed on time for the project to be completed on schedule.
It involves analyzing the dependencies between tasks and determining the longest path of tasks, called the critical path, that must be completed on time for the project to be completed on schedule.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following tasks is considered to be a defining (really important) task in project management?
Marketing and advertising the project results
Managing and allocating project resources
Conducting project risk analysis
Planning employee vacation schedules
Answer explanation
Managing and allocating project resources is considered a defining task in project management because it is a crucial task that helps ensure the successful completion of a project.
Allocating the right resources, such as personnel, equipment, and materials, to the right tasks at the right time is essential for keeping a project on schedule and within budget.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following methods is considered to be the most accurate for estimating the duration of tasks in project management?
Three-point estimation
Expert judgment
Analogous estimation
Bottom-up estimation
Answer explanation
Bottom-up estimation is considered to be the most accurate method for estimating the duration of tasks in project management.
This method involves breaking down the project into smaller, more manageable tasks, and then estimating the duration of each individual task.
Time consuming...
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT a tool or technique used for identifying dependencies between tasks in project management?
Network diagrams
Predecessor and successor tables
Gantt charts
Surveying team members
Answer explanation
Surveying team members is not a tool or technique used for identifying dependencies between tasks in project management.
Surveying team members is a method to gather information and feedback from team members, but it is not directly used to identify dependencies between tasks.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT a characteristic of the critical path?
It is the longest path through the project network
It has the least amount of total float
It has the least amount of free float
It is the shortest path through the project network
Answer explanation
The critical path is the longest path in a project network diagram.
It is the sequence of tasks that must be completed on time for the project to be completed on schedule.
It has the least amount of total float, which is the amount of time a task can be delayed without delaying the completion of the project.
And the least amount of free float, which is the amount of time a task can be delayed without delaying the start of its successor task.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Schedule Variance (SV) is calculated by:
Subtracting the planned value from the earned value (EV - PV)
Subtracting the earned value from the planned value (PV - EV)
Subtracting the actual cost from the planned cost (PC - AC)
Subtracting the planned cost from the actual cost (AC - PC)
Answer explanation
Schedule Variance (SV) is a measure used to assess the performance of a project schedule.
It is calculated by subtracting the Planned Value (PV) from the Earned Value (EV)
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
internships

Quiz
•
University - Professi...
15 questions
Operation Management - Chapter 7 & 8

Quiz
•
University
10 questions
Communication & Collaboration Technology

Quiz
•
University
15 questions
Project Management Final Quizz

Quiz
•
University
10 questions
1 - The World of Marketing

Quiz
•
University
8 questions
Revision MGMT8360

Quiz
•
University
10 questions
INTERNAL ENVIRONMENTAL ANALYSIS

Quiz
•
University
15 questions
PPT 01 PART 1

Quiz
•
University
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
20 questions
Brand Labels

Quiz
•
5th - 12th Grade
15 questions
Core 4 of Customer Service - Student Edition

Quiz
•
6th - 8th Grade
15 questions
What is Bullying?- Bullying Lesson Series 6-12

Lesson
•
11th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade