Project Management Plan Schedule - D2

Project Management Plan Schedule - D2

University

10 Qs

quiz-placeholder

Similar activities

Chap 4: Organizing

Chap 4: Organizing

University

15 Qs

Organizational Structure

Organizational Structure

University

10 Qs

What do you know about organizational behavior?

What do you know about organizational behavior?

University

10 Qs

HOW IS YOUR TIME MANAGEMENT

HOW IS YOUR TIME MANAGEMENT

University

15 Qs

PJMT 2203: Week 6: PM Cost Management

PJMT 2203: Week 6: PM Cost Management

University

10 Qs

2. Project Management and Organization

2. Project Management and Organization

University

15 Qs

Communication, Conflict Management & Negotiation Quiz

Communication, Conflict Management & Negotiation Quiz

University

15 Qs

Project Management Plan Schedule - D2

Project Management Plan Schedule - D2

Assessment

Quiz

Business

University

Medium

Created by

Paolino Kitieu

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project management plan, what is the purpose of the schedule?

  • To identify and mitigate project risks

  • To define and communicate specific, measurable, achievable, relevant, and time-bound goals and objectives

  • To outline the specific tasks, milestones, and deadlines for completing the project

  • To allocate resources and assign tasks to team members

Answer explanation

In a project management plan, the schedule is a critical component that outlines the specific tasks, milestones, and deadlines for completing the project.

It is a visual representation of the project, usually in the form of a Gantt chart or network diagram, which shows the dependencies between tasks and the critical path of the project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes the application of the critical path method (CPM)?

  • A tool used to identify and mitigate project risks

  • A method for tracking and managing project costs

  • A technique for identifying the sequence of project tasks that must be completed on time in order for the project to be completed on schedule

  • A method for allocating resources and assigning tasks to team members

Answer explanation

CPM is a project management technique used to identify the sequence of project tasks that must be completed on time for the project to be completed on schedule.

It involves analyzing the dependencies between tasks and determining the longest path of tasks, called the critical path, that must be completed on time for the project to be completed on schedule.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following tasks is considered to be a defining (really important) task in project management?

  • Marketing and advertising the project results

  • Managing and allocating project resources

  • Conducting project risk analysis

  • Planning employee vacation schedules

Answer explanation

Managing and allocating project resources is considered a defining task in project management because it is a crucial task that helps ensure the successful completion of a project.

Allocating the right resources, such as personnel, equipment, and materials, to the right tasks at the right time is essential for keeping a project on schedule and within budget.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following methods is considered to be the most accurate for estimating the duration of tasks in project management?

  • Three-point estimation

  • Expert judgment

  • Analogous estimation

  • Bottom-up estimation

Answer explanation

Bottom-up estimation is considered to be the most accurate method for estimating the duration of tasks in project management.

This method involves breaking down the project into smaller, more manageable tasks, and then estimating the duration of each individual task.

Time consuming...

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a tool or technique used for identifying dependencies between tasks in project management?

  • Network diagrams

  • Predecessor and successor tables

  • Gantt charts

  • Surveying team members

Answer explanation

Surveying team members is not a tool or technique used for identifying dependencies between tasks in project management.

Surveying team members is a method to gather information and feedback from team members, but it is not directly used to identify dependencies between tasks.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a characteristic of the critical path?

  • It is the longest path through the project network

  • It has the least amount of total float

  • It has the least amount of free float

  • It is the shortest path through the project network

Answer explanation

The critical path is the longest path in a project network diagram.

It is the sequence of tasks that must be completed on time for the project to be completed on schedule.

It has the least amount of total float, which is the amount of time a task can be delayed without delaying the completion of the project.

And the least amount of free float, which is the amount of time a task can be delayed without delaying the start of its successor task.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Schedule Variance (SV) is calculated by:

  • Subtracting the planned value from the earned value (EV - PV)

  • Subtracting the earned value from the planned value (PV - EV)

  • Subtracting the actual cost from the planned cost (PC - AC)

  • Subtracting the planned cost from the actual cost (AC - PC)

Answer explanation

Schedule Variance (SV) is a measure used to assess the performance of a project schedule.

It is calculated by subtracting the Planned Value (PV) from the Earned Value (EV)

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?