CPM - Pertemuan ke-6

CPM - Pertemuan ke-6

University

5 Qs

quiz-placeholder

Similar activities

Pre Test-13

Pre Test-13

University

10 Qs

Building Basics

Building Basics

10th Grade - University

10 Qs

Embedded Systems

Embedded Systems

University

10 Qs

Alpro 2 Mg 1 - Understanding C++ Basics

Alpro 2 Mg 1 - Understanding C++ Basics

University

10 Qs

MechnoSpell Challenge-002

MechnoSpell Challenge-002

University

10 Qs

Engineering Professional Bodies & Ethics

Engineering Professional Bodies & Ethics

University

10 Qs

IUCEE ConQuest: The Ultimate Technical Quiz Challenge

IUCEE ConQuest: The Ultimate Technical Quiz Challenge

University

10 Qs

AI BASED CREATIVE QUIZ

AI BASED CREATIVE QUIZ

University

10 Qs

CPM - Pertemuan ke-6

CPM - Pertemuan ke-6

Assessment

Quiz

Engineering

University

Practice Problem

Easy

Created by

Frieska Ariesta

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Critical Path adalah aktivitas yang?

Tidak memiliki float

Memiliki free float

Memiliki total float

Menunda proyek

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Tertundanya Critical Activities tidak mempengaruhi penyelesaian proyek

Benar

Salah

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Aktivitas pada critical path disebut?

project milestone

critical path activity

project activity

schedule activity

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Sebuah proyek bisa memiliki lebih dari satu critical path

Salah

Benar

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Metode yang memperhitungkan waktu early start dan early finish pada schedule network disebut?

Penghitungan Mundur

Penghitungan Maju

Estimasi tiga poin

Teknik Analitis