Planning Quiz

Planning Quiz

12th Grade

10 Qs

quiz-placeholder

Similar activities

t-level Construction Project Documentation Quiz

t-level Construction Project Documentation Quiz

12th Grade

15 Qs

Info & data PPT 6 quiz

Info & data PPT 6 quiz

12th Grade

15 Qs

8202 211 ppt1 Health & Safety in the Construction Industry Quiz

8202 211 ppt1 Health & Safety in the Construction Industry Quiz

12th Grade

15 Qs

Metals in Plumbing Quiz

Metals in Plumbing Quiz

12th Grade

15 Qs

00107 Communication skills

00107 Communication skills

9th - 12th Grade

10 Qs

Quiz tentang BIM dan Autodesk Revit

Quiz tentang BIM dan Autodesk Revit

12th Grade

15 Qs

PPT 3 - Pipework & Circulation COL

PPT 3 - Pipework & Circulation COL

12th Grade - University

15 Qs

Construction Industry Trivia Challenge

Construction Industry Trivia Challenge

12th Grade - University

15 Qs

Planning Quiz

Planning Quiz

Assessment

Quiz

Construction

12th Grade

Hard

Created by

Paul Humphreys

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first stage of a typical construction project?

Tendering

Construction

Design

Maintenance

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who creates the working drawings based on the client’s requirements?

Quantity Surveyor

Architect

Clerk of Works

Estimator

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does an estimator do during the tendering process?

Supervises construction work

Inspects the quality of the work

Calculates the project's total cost

Creates the building design

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a fixed-price contract, who covers increased costs after the contract is signed?

Client

Contractor

Estimator

Subcontractor

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What document lists all the parts needed to build a product?

Specification

Take-off sheet

Drawing

Bill of Materials

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which role is responsible for inspecting and checking work on-site?

Clerk of Works

Contracts Manager

Estimator

Project Manager

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of these is part of the electrical project stages?

Planning

Design

Evaluation

Inspection

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?