When a contractor submits a “Contractor’s Application for Payment,” to the architect, how long does the architect have to formally issue to the Owner a “Certificate for Payment” or to notify the contractor and the owner of the architects’ reason for withholding certification?

A201 Contract Quiz

Quiz
•
Architecture
•
University
•
Hard
AIAS University of Southern California
Used 1+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
7 days
14 days
One month
One pay cycle
2.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
Which of the following is NOT a valid reason for the architect withholding certification of payment?
A. defective Work not remedied
B. third party claims filed or reasonable evidence indicating probable filing of such claims, unless security acceptable to the Owner is provided by the Contractor
C. the payment request includes the cost of materials for construction that are stored off-site
D. failure of the Contractor to make payments properly to Subcontractors or suppliers for labor, materials or equipment
3.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
Which of the following is NOT a valid reason for the architect withholding certification of payment?
A. reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum
B. the architect was too busy working on their studio project to complete the assignment
C. reasonable evidence that the Work will not be completed within the Contract Time, and that the unpaid balance would not be adequate to cover actual or liquidated damages for the anticipated delay
D. repeated failure to carry out the Work in accordance with the Contract Documents.
4.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
The contractor shall take reasonable precautions for the safety and protect of each of these EXCEPT:
A. Employees on the Work and other persons who may be affected
B. The Work, materials, and equipment
C. Utilities designated for removal or replacement
D. Other property at the site or adjacent (such as trees, sidewalks, etc.)
5.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
After injury to a person or damage to property by any party, notice must be made to other party within:
A. One calendar day
B. 24 hours from the time of the incident
C. One week
D. 21 days
6.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
Who pays for the costs of remediation for failure to comply with requirements regarding hazardous materials and substances?
A. Contractor
B. Owner
C. Both contractor and owner equally
D. The contractor unless the remediation is due to the owner’s fault or negligence
7.
MULTIPLE CHOICE QUESTION
20 sec • 5 pts
Which party (or parties) shall be included on the Contractor’s commercial general liability insurance policy?
A. Owner
B. Owner and Architect
C. Owner and Architect and Architect’s Consultants
D. None of the above
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
Professional Practice Quiz#3

Quiz
•
University
15 questions
PD 1096

Quiz
•
University
10 questions
Architecture

Quiz
•
University
10 questions
SITE VISIT QUIZ

Quiz
•
University
13 questions
3-3 Administrative Procedures & Protocols

Quiz
•
University
14 questions
2-3 Contracts

Quiz
•
University
11 questions
3-2 Construction Observation

Quiz
•
University
10 questions
L1: Overview of Building Science & Services I

Quiz
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade