Project Management Quiz

Project Management Quiz

University

101 Qs

quiz-placeholder

Similar activities

TEST -17- My First Acquaintance with Poets, Lyrical Ballads

TEST -17- My First Acquaintance with Poets, Lyrical Ballads

University

100 Qs

N2: Examen final (tercer parcial)

N2: Examen final (tercer parcial)

University

100 Qs

English Language Quiz

English Language Quiz

12th Grade - University

100 Qs

Tes Wawasan KIPK 2023

Tes Wawasan KIPK 2023

12th Grade - University

100 Qs

REVIEW - SIMPLE PAST VS PAST CONTINUOUS

REVIEW - SIMPLE PAST VS PAST CONTINUOUS

University

106 Qs

Can for ability

Can for ability

University

100 Qs

English Bridge Program BATCH 1

English Bridge Program BATCH 1

University

100 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

English

University

Practice Problem

Easy

Created by

Vi Lan

Used 6+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

101 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

The traditional competing constraints on a project are:

Time, cost, and profitability

Resources required, sponsorship involvement, and funding

Time, cost, and quality and/or scope

Calendar dates, facilities available, and funding

2.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Which of the following is not part of the definition of a project?

Repetitive activities

Constraints

Consumption of resources

A well-defined objective

3.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Which of the following is usually not part of the criteria for project success?

Customer satisfaction

Customer acceptance

Meeting at least 75 percent of specification requirements.

Meeting the triple-constraint requirements

4.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Which of the following is generally not a benefit achieved from using project management?

Flexibility in the project’s end date

Improved risk management

Improved estimating

Tracking of projects

5.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

The person responsible for assigning the resources to a project is most often:

The project manager

The Human resources Department

The line manager

The executive sponsor

6.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Conflicts between the project and line managers are most often resolved by:

The assistant project manager for conflicts

The project sponsor

The executive steering committee

The Human resources Department

7.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Your company does only projects. If the projects performed by your company are for customers external to your company and a profit criterion exists on the project, then your organization is most likely:

Project-driven

Non–project-driven

A hybrid

All of the above are possible based upon the size of the profit margin

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?