Interim Payments Quiz
Authored by Muhammad Nasrol Jamal
Other
University

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the percentage of progressive cost to net contract sum?
2.91619%
3.5%
1.5%
4.0%
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the amount of preliminaries to be paid if the net value of work executed by the contractor to date is RM900,000.00?
RM26,245.71
RM30,000.00
RM20,000.00
RM15,000.00
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
According to Clause 28.4, what must be included in the interim certificate?
The estimated total value of the work properly executed
Only the value of work improperly executed
The total contract sum
The value of work not executed
4.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What are the prerequisites for payment regarding materials on site?
Delivered to site or adjacent to site
Intended for incorporation in the permanent works
Reasonably, properly and not prematurely brought to site
Adequately protected against weather and casualties
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What must the contractor obtain regarding the goods?
Adequate title to the goods
Payment from the employer
Delivery confirmation
Supplier's invoice
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What percentage of the total value of materials is to be paid to the contractor?
80%
90%
100%
70%
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What must the type and quality of materials comply with?
Specifications stated in the contract
Market prices
Supplier's recommendations
Local regulations
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?