PMI-CP_M3_Contract and Risk

PMI-CP_M3_Contract and Risk

Professional Development

50 Qs

quiz-placeholder

Similar activities

ECBA Exam 3

ECBA Exam 3

Professional Development

50 Qs

PROF PRAC: SITUATIONAL

PROF PRAC: SITUATIONAL

Professional Development

50 Qs

CSTN2395 Project Management Final (textbook questions)

CSTN2395 Project Management Final (textbook questions)

Professional Development

46 Qs

PMP 380 mock questions - Chapter 2 (Process)

PMP 380 mock questions - Chapter 2 (Process)

Professional Development

50 Qs

Weekend Quiz

Weekend Quiz

Professional Development

50 Qs

PMI ACP SG NOKIA Agile Extra 45 Qns

PMI ACP SG NOKIA Agile Extra 45 Qns

Professional Development

45 Qs

PMI BC Quiz 1

PMI BC Quiz 1

Professional Development

45 Qs

Project Management Fundamental : Post-test

Project Management Fundamental : Post-test

Professional Development

50 Qs

PMI-CP_M3_Contract and Risk

PMI-CP_M3_Contract and Risk

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Benigno Cruz

Used 1+ times

FREE Resource

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Undertaking market analysis and benchmarking on previous projects provides owner organizations with what?

Insights into the future.

Data to help guide cost estimations, and schedules.

Constructability reviews

Interim designs.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Bid calculation is part of the tendering or proposal process.

True

False

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which clause will be used to transfer a specific event risk from one entity to another, such as site accident risk?

Change clause.

Payment clause.

Indemnity clause.

Time-barred clause.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Design-bid -build is the most commonly used method for completing built environment projects.

True

False

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following is not one of the seven most common types of contract payment structures:

Lump- sum.

Cost plus a fee.

Cost plus a fee with guaranteed maximum price (GMP).

Cost minus a fee.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Pricing is one of the most common contract risks.

True

False

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The first step in the risk management process is Identification.

True

False

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?