1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A recently appointed project manager takes charge of a project initiated last year focused on renovating a bustling airport terminal.
Even though the project uses a hybrid development approach—making incremental updates to the terminal—it has encountered many issues, especially creating conflicts with airport operations. The recently appointed project manager inquires with the project team about their usual approach to managing problems and risks, but none of the team members provide a definite response.
What should the project manager do first?
Modify the risk register
Switch to a predictive approach for better risk management
Start to identify potential risks
Update the risk management plan
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Luna is working on a construction project that spans over 12 months. She reviews the schedule and notice that there are times when certain team members on her project team are severely over allocated, which means she might need to bring on extra resources to help handle the extra load.
However, at other times during her project the team is under-allocated, which means she may have to lay off some team members.
Which of the following should she does to rearrange her resources so that a priority given to constant number of resources are used in the project?
Crashing
Resource Smoothing
Fast Tracking
Resource Leveling
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
April is a project manager at her organization. She is currently assigned to work on a project to migrate a large number of servers from an on-site data center at her organization to an off-site data center that is monitored 24/7 by a third party vendor. The company believes this offloading will increase efficiency and reduce work requirements in areas where the company is not specialized.
April is putting together the project requirements, constraints, and assumptions. Which document is April likely working on?
April is gathering the project requirements so she is probably working on the Project Management Plan
The Project Scope Statement is the document that contains the project requirements, the constraints on the project, and the assumptions used
April is drafting the Project Charter so that she can start work on her project
April is most likely drafting the Communications Management Plan since the project constraints usually deal with the project communications and when everyone is unavailable for meetings
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Niclole is the project manager of the Raffles MIS Project. This project is to create a new software package for a client. She is working with the client, business analysts, software developers, business developers, and the sales team to create the vision and requirements of the newly initiated project.
Of the following, which one determines the scope of the project?
The customer and the stakeholders
The project sponsor
The performing organizations management
The project manager
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model?
This schedule network analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without regard to any resource limitations by performing a forward and backward pass analysis through the schedule network.
Schedule Compression
Critical Chain Method
Critical Path Method
PERT
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Angie is a project manager for her organization. Her current project assignment is with a team that is working to construct a component that will be used in a shuttle that will be launched by a commercial space travel organization.
The client corporation has stringent quality requirements that must be adhered to, otherwise the component could endanger the lives of the passengers on the shuttle.
Angie should be concerned with the quality attributes of the product her team is building.
Which statement best describes quality attributes in this context?
The quality attributes of the component Angie’s team is build are the acceptance criteria that are to be met mandatorily
The quality attributes of that Angie is concerned about provide a basis for judging a project's success or failure
The quality attributes that Angie is referencing in this situation provide a basis for determining how effectively Angie’s organization supports the project
The quality attributes are the specific characteristics for which Angie’s team`s product is designed and tested
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Elements of the project that are well known or have fixed requirements follow a predictive development life cycle, and those elements that are still evolving follow an adaptive development life cycle. Which of the following project life cycle types does this statement refer to?
Iterative Life Cycle
Adaptive Life Cycle
Predictive Life Cycle
Hybrid Life Cycle
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
70 questions
REGLAMENTO KUMITE 2024 (4.1)
Quiz
•
Professional Development
65 questions
Tes Kompetensi Teknis Kesehatan Umum
Quiz
•
Professional Development
65 questions
65 câu Lý Sinh
Quiz
•
Professional Development
70 questions
Soal II PMR (7 Materi) Kak Doif
Quiz
•
Professional Development
69 questions
RT Boeing 737
Quiz
•
Professional Development
67 questions
Bell 412 - ATA 24 - Electrical
Quiz
•
Professional Development
72 questions
418 Applications of the Science of Reading Practice Test
Quiz
•
Professional Development
63 questions
2016
Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade