What must be established before and after using explosives for demolition?
Demolition Quiz

Quiz
•
Construction
•
9th Grade
•
Hard
E Donovan-Bayley
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Safety nets
Exclusion zones
Water barriers
Noise barriers
Answer explanation
Exclusion zones must be established before and after using explosives for demolition to ensure the safety of individuals and property in the surrounding area.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which method of demolition is slower and completed by workmen?
Explosives
Machine
Hand Demolition
Hydraulic pushing arm
Answer explanation
Hand Demolition is slower and completed by workmen, making it the correct choice for a method of demolition that fits the description.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the final step in the six steps to demolition?
Pre-Demolition Survey
Check for Asbestos
Approve Demolition Plan
Have a waste disposal plan
Answer explanation
The final step in the six steps to demolition is to have a waste disposal plan.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is it important to have a waste disposal plan in demolition?
To ensure the building is structurally sound
To prevent health hazards
To manage debris and waste materials
To save costs
Answer explanation
To manage debris and waste materials
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the acronym "BS" in BS 6817 stand for?
British Standards
Building Standards
Basic Standards
Building Safety
Answer explanation
The acronym 'BS' in BS 6817 stands for British Standards, making it the correct choice among the options provided.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which step involves ensuring the building is free from hazardous materials?
Disconnect water/gas/electric
Check for Asbestos
Warn people in local area
Waste Disposal Plan
Answer explanation
The step that involves ensuring the building is free from hazardous materials is to Check for Asbestos.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be disconnected before demolition begins?
Water, gas, and electric
Internet and phone lines
Sewage and drainage
Heating and cooling systems
Answer explanation
Before demolition begins, it is crucial to disconnect water, gas, and electric to ensure safety and prevent accidents during the process.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Building Operations and renovations

Quiz
•
9th Grade
10 questions
307 Central Heating Systems 3 Quiz

Quiz
•
2nd Grade - University
10 questions
PRINCON Safety and Health Regulations Quiz

Quiz
•
9th Grade
9 questions
Sustainable Construction

Quiz
•
9th Grade
11 questions
Construction and Environmental Impact Quiz

Quiz
•
9th Grade
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade