PMI SP Schedule Planning and Development

PMI SP Schedule Planning and Development

Professional Development

13 Qs

quiz-placeholder

Similar activities

Alestra Diagnóstico

Alestra Diagnóstico

Professional Development

15 Qs

Post-test Project Management

Post-test Project Management

Professional Development

10 Qs

Project Scope Management

Project Scope Management

Professional Development

10 Qs

Project Management

Project Management

Professional Development

9 Qs

SFS Quiz All Hands

SFS Quiz All Hands

Professional Development

9 Qs

November W III - 1

November W III - 1

Professional Development

15 Qs

All-In-One Project+ PK0-005 Exam Guide - Chapter 09

All-In-One Project+ PK0-005 Exam Guide - Chapter 09

Professional Development

15 Qs

Project Schedule Management

Project Schedule Management

Professional Development

15 Qs

PMI SP Schedule Planning and Development

PMI SP Schedule Planning and Development

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

PMI Trainer

Used 7+ times

FREE Resource

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is NOT a key component of project scheduling?

WBS (Work Breakdown Structure)

Risk register

Gantt chart

Network diagram

Dependencies and logic

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the critical path in project scheduling?

The longest path in the project network diagram with shortest time to complete the project

The path with the highest resource utilization and all complex activities

The path with the most dependencies

The path that requires the most complex activities to complete the project

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of a schedule model in the schedule approach?

To establish the project timeline and milestones with a methodology choosen

To identify and analyze project risks

To define the project's work breakdown structure (WBS)

To allocate resources to project activities

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which scheduling technique is commonly used to allocate resources to project activities?

Critical Path Method (CPM)

Precedence Diagramming Method (PDM)

Resource levelling

Monte Carlo simulation

All of the above

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the significance of identifying near-critical paths in project scheduling?

Near-critical paths have the highest resource utilisation

Near-critical paths have the least number of dependencies

Near-critical paths have the potential to become critical paths

Near-critical paths are not important for project scheduling

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the role of resource calendars in defining the resource-constrained schedule?

To allocate resources to project activities

To track changes and variances in resource utilization

To establish a reference point for project control

To define resource availability and working hours

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does the Performance Measurement Baseline (PMB) typically include?

Project scope statement and objectives

Project resource allocation plan

Approved project schedule, SOW, WBS and milestones

Risk register and mitigation strategies

All of these

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?