PMI SP Schedule strategy
Quiz
•
Professional Development
•
Professional Development
•
Medium
PMI Trainer
Used 6+ times
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
All of the project team members are unable to manage their project working shifts. What is the primary objective for the schedule strategy which you are creating?
Allocation of resources for the procurement
Managing project risks
Allocation of resources across the project
Setting project goals to make sure the resources work in right shifts
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Schedule development starts after___________
Project goals are finalized
Project scope is delivered
project vision is finalized
project scope if finalized
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
what are foundations for formulating project scope
Strategic goals, objectives, performance outcome
Strategic goals, outcome, performance outcome
goals, benefits, outcome
WBS, project scope statement (SOW), Baseline
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your client ABC is asking PM to submit the schedule report biweekly but your company is asking you to to submit once in a month to clients. What do you do?
Submit monthly as per company guidelines
Submit biweekly as per customer requirement by intimating company
Let both parties come to a conclusion and keep the submission on hold until a decision is arrived
Submit offline report to your client without intimating company
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the purpose of a schedule baseline in the schedule approach?
To track changes and variances in the project schedule
To document project risks and mitigation strategies
To allocate resources to project activities
To establish a reference point for project performance control
To celebrate the success and justify the client with efforts
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following factors should be considered when determining the appropriate scheduling methodology for a project?
Project size and complexity
Project budget and cost constraints
Stakeholder expectations and requirements
All of the above
Organizational governance
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is one of the main objective of defining the resource-constrained schedule?
To optimize the allocation of project resources
To identify critical paths in the project schedule
To estimate project costs accurately
To determine project risks and uncertainties
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple

Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
13 questions
PMP Exam Preparation Mocktest With Formula
Quiz
•
Professional Development
10 questions
Programming and Planning Quiz
Quiz
•
Professional Development
10 questions
CASHE 2.0 2025 Workshop
Quiz
•
Professional Development
20 questions
SOAL LATIHAN TES GURU P3K - PEDAGOGIK
Quiz
•
Professional Development
10 questions
Junior Si - Educator Quiz
Quiz
•
Professional Development
12 questions
Contributing to the delivery of a project
Quiz
•
Professional Development
20 questions
Project Management Basics Quiz
Quiz
•
Professional Development
11 questions
Practice Exam 2 Part 1
Quiz
•
Professional Development
Popular Resources on Wayground
20 questions
Brand Labels
Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
20 questions
ELA Advisory Review
Quiz
•
7th Grade
15 questions
Subtracting Integers
Quiz
•
7th Grade
22 questions
Adding Integers
Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns
Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials
Interactive video
•
6th - 10th Grade