PMI SP Schedule strategy
Authored by PMI Trainer
Professional Development
Professional Development
Used 6+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
All of the project team members are unable to manage their project working shifts. What is the primary objective for the schedule strategy which you are creating?
Allocation of resources for the procurement
Managing project risks
Allocation of resources across the project
Setting project goals to make sure the resources work in right shifts
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Schedule development starts after___________
Project goals are finalized
Project scope is delivered
project vision is finalized
project scope if finalized
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
what are foundations for formulating project scope
Strategic goals, objectives, performance outcome
Strategic goals, outcome, performance outcome
goals, benefits, outcome
WBS, project scope statement (SOW), Baseline
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your client ABC is asking PM to submit the schedule report biweekly but your company is asking you to to submit once in a month to clients. What do you do?
Submit monthly as per company guidelines
Submit biweekly as per customer requirement by intimating company
Let both parties come to a conclusion and keep the submission on hold until a decision is arrived
Submit offline report to your client without intimating company
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the purpose of a schedule baseline in the schedule approach?
To track changes and variances in the project schedule
To document project risks and mitigation strategies
To allocate resources to project activities
To establish a reference point for project performance control
To celebrate the success and justify the client with efforts
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following factors should be considered when determining the appropriate scheduling methodology for a project?
Project size and complexity
Project budget and cost constraints
Stakeholder expectations and requirements
All of the above
Organizational governance
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is one of the main objective of defining the resource-constrained schedule?
To optimize the allocation of project resources
To identify critical paths in the project schedule
To estimate project costs accurately
To determine project risks and uncertainties
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?