PMI SP Schedule strategy

PMI SP Schedule strategy

Professional Development

15 Qs

quiz-placeholder

Similar activities

Energizer quiz-Recapitulation-Group 3

Energizer quiz-Recapitulation-Group 3

Professional Development

10 Qs

Resource Mgmt Pre-test

Resource Mgmt Pre-test

Professional Development

10 Qs

PMP Prep Quiz - 1,2,3

PMP Prep Quiz - 1,2,3

Professional Development

10 Qs

Canva Features for Group

Canva Features for Group

Professional Development

10 Qs

Project Execution & Monitoring

Project Execution & Monitoring

Professional Development

12 Qs

SG20_Test_S5_CH6 Schedule

SG20_Test_S5_CH6 Schedule

Professional Development

10 Qs

Project Management

Project Management

Professional Development

15 Qs

Business English 1

Business English 1

Professional Development

20 Qs

PMI SP Schedule strategy

PMI SP Schedule strategy

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

PMI Trainer

Used 6+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

All of the project team members are unable to manage their project working shifts. What is the primary objective for the schedule strategy which you are creating?

Allocation of resources for the procurement

Managing project risks

Allocation of resources across the project

Setting project goals to make sure the resources work in right shifts

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Schedule development starts after___________

Project goals are finalized

Project scope is delivered

project vision is finalized

project scope if finalized

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

what are foundations for formulating project scope

Strategic goals, objectives, performance outcome

Strategic goals, outcome, performance outcome

goals, benefits, outcome

WBS, project scope statement (SOW), Baseline

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your client ABC is asking PM to submit the schedule report biweekly but your company is asking you to to submit once in a month to clients. What do you do?

Submit monthly as per company guidelines

Submit biweekly as per customer requirement by intimating company

Let both parties come to a conclusion and keep the submission on hold until a decision is arrived

Submit offline report to your client without intimating company

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of a schedule baseline in the schedule approach?

To track changes and variances in the project schedule

To document project risks and mitigation strategies

To allocate resources to project activities

To establish a reference point for project performance control

To celebrate the success and justify the client with efforts

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following factors should be considered when determining the appropriate scheduling methodology for a project?

Project size and complexity

Project budget and cost constraints

Stakeholder expectations and requirements

All of the above

Organizational governance

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is one of the main objective of defining the resource-constrained schedule?

To optimize the allocation of project resources

To identify critical paths in the project schedule

To estimate project costs accurately

To determine project risks and uncertainties

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?

Discover more resources for Professional Development