Plumbing level 2 - PP6 - Hot water

Plumbing level 2 - PP6 - Hot water

University

10 Qs

quiz-placeholder

Similar activities

PRETEST-2 BPJ

PRETEST-2 BPJ

University

15 Qs

Plumbing level 2 - PP3 - Drainage

Plumbing level 2 - PP3 - Drainage

University

10 Qs

Hydronic Heating Terms and Definitions

Hydronic Heating Terms and Definitions

University

10 Qs

air brake component & understanding

air brake component & understanding

University

12 Qs

Week 16 - Primary Survey Recap

Week 16 - Primary Survey Recap

University - Professional Development

12 Qs

AS YOU CAN SEE ....

AS YOU CAN SEE ....

10th Grade - Professional Development

13 Qs

UNDERSTANDING THE SELF ASSESSMENT

UNDERSTANDING THE SELF ASSESSMENT

University

10 Qs

NFPA 25 5.5 Review quiz

NFPA 25 5.5 Review quiz

University

10 Qs

Plumbing level 2 - PP6 - Hot water

Plumbing level 2 - PP6 - Hot water

Assessment

Quiz

Professional Development

University

Easy

Created by

Byron Morris

Used 67+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be done before starting soundness testing?

Attach the hydraulic test bucket

Pump system up to working pressure

Check for open ends and tight joints

Fill the system with water

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in soundness testing for rigid pipes?

Leave for one hour

Slowly fill the system with water

Check for any pressure drop

Pump system up to 1.5 times the working pressure

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For plastic pipe soundness testing (Test A), what should the pressure be increased to after 45 minutes?

1.5 times working pressure

Manufacturer’s test pressure

1 bar

2 times working pressure

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In plastic pipe soundness testing (Test B), what is the acceptable total pressure loss after 120 minutes?

Less than 0.1 bar

Less than 0.2 bar

Less than 0.3 bar

Less than 0.4 bar

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be done after filling the system with water during flushing and disinfecting?

Add disinfectant to system

Open all draw-off points

Drain system from the lowest point

Test chlorine levels at each outlet

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of adding disinfectant to the system during flushing and disinfecting?

To stabilize temperature

To check for leaks

To disinfect the pipes

To remove debris

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be done to ensure correct operation of blending valves?

Flush through as per BS6700

Test chlorine levels

Check for leaks

Ensure correct temperature is set and recorded

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?