UL s12

UL s12

Professional Development

6 Qs

quiz-placeholder

Similar activities

Agile Testing Quiz 1

Agile Testing Quiz 1

Professional Development

10 Qs

Función CONTAR

Función CONTAR

KG - Professional Development

10 Qs

Tarjetas gráficas

Tarjetas gráficas

Professional Development

10 Qs

Unidad 6 Windows 10

Unidad 6 Windows 10

Professional Development

10 Qs

Evaluación cuarto

Evaluación cuarto

1st Grade - Professional Development

11 Qs

ITIC - semana 6

ITIC - semana 6

Professional Development

10 Qs

Repaso_Procesador_Texto

Repaso_Procesador_Texto

Professional Development

10 Qs

ERP rendszerek

ERP rendszerek

1st Grade - Professional Development

10 Qs

UL s12

UL s12

Assessment

Quiz

Computers

Professional Development

Practice Problem

Hard

Created by

Diego Helfer

Used 10+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Es una entrada de MRP

MPS

Material

Reportes de Excepción

Ordenes de Compra

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Es una salida del MRP

MPS

Lista de Materiales

Plan de Materiales

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Cual no forma parte del área de ventas

Ventas

Sector

Canal

Puesto de expedición

4.

FILL IN THE BLANK QUESTION

20 sec • 1 pt

Como se le conoce al Plan Maestro de Requerimientos

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

En una empresa de fabricación, un Plan Maestro de Requerimientos no depende de un plan maestro de producción

Falso

Verdadero

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Es necesario ingresar la fecha de despacho al crear un pedido de venta

No

Si