Project Management Quiz

Project Management Quiz

University

20 Qs

quiz-placeholder

Similar activities

SIA101 - Assignment 1

SIA101 - Assignment 1

University

16 Qs

Entrepreneurship Development & Business Strategies: BHCT-408

Entrepreneurship Development & Business Strategies: BHCT-408

University

20 Qs

BeT - Xmas Quiz 2021

BeT - Xmas Quiz 2021

University

21 Qs

MAF661 : CHAPTER 6 & 8

MAF661 : CHAPTER 6 & 8

University

20 Qs

PM - Chap 12

PM - Chap 12

University

17 Qs

REVISION ISC500

REVISION ISC500

University

21 Qs

intro to PM

intro to PM

University

20 Qs

Chapter 4 Organization Structure & Design

Chapter 4 Organization Structure & Design

University

15 Qs

Project Management Quiz

Project Management Quiz

Assessment

Quiz

Business

University

Hard

Created by

Keisha Muhangi

Used 1+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of organizational structure is described by a matrix organization?

A team structure with members from the same functional area

A hierarchical team structure with a clear chain of command

A team structure with members from functional areas, depending on skills required

A decentralized team structure without any functional boundaries

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is considered the most important member of a project team?

The CEO of the company

The project coordinator

The project manager

The lead engineer

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a scope statement in project management?

To outline the budget of a project

To provide an understanding, justification, and expected result of a project

To list the team members involved in a project

To set the timeline for project completion

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a Statement of Work (SOW) typically include?

A graphical representation of the project timeline

A detailed budget breakdown

A written description of the objectives of a project

A list of potential risks and mitigation strategies

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary function of a Work Breakdown Structure (WBS) in project management?

To provide financial oversight

To manage project communications

To organize a project into manageable sections

To finalize project deliverables

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in the work breakdown structure for designing an information interface for a new sales knowledge management system in an insurance company?

Install systems

Form and train user group

Design initial screen interface

Specify sales training

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which phase follows the 'Training' phase in the work breakdown structure presented?

Testing

Installation

Modification

Design

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?