1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is project scope definition?

Project scope definition is the process of creating a detailed project schedule.

Project scope definition is the process of selecting the best project management software.

Project scope definition is the process of determining and documenting a list of specific project goals, deliverables, features, functions, tasks, deadlines, and ultimately costs.

Project scope definition is the process of determining and documenting a list of team members for the project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can scope creep be managed effectively?

Ignoring changes, increasing the budget, skipping stakeholder communication

By defining project requirements, setting up a change control process, communicating with stakeholders, and prioritizing tasks.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Explain the concept of Work Breakdown Structure (WBS) in project management.

Work Breakdown Structure (WBS) is only used in agile project management methodologies

The concept of Work Breakdown Structure (WBS) involves combining all project tasks into one large deliverable

WBS is a tool used for resource allocation in project management

The concept of Work Breakdown Structure (WBS) in project management involves breaking down the project into smaller tasks, subtasks, and deliverables to organize and manage the work effectively.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of scope verification process?

To confirm that all completed work aligns with the project scope.

To assign tasks to team members

To track project milestones

To determine the project budget

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is scope change control important in project management?

Scope change control leads to increased scope creep

Scope change control is unnecessary and hinders project progress

Scope change control limits project flexibility

Scope change control is important in project management to prevent scope creep, maintain project focus, and manage resources effectively.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Describe the steps involved in developing a scope statement.

Identify project objectives, identify project deliverables, create a work breakdown structure (WBS), define project scope boundaries, obtain approval from stakeholders.

Define project objectives, skip project deliverables, create a work breakdown structure (WBS), define project scope boundaries, obtain approval from stakeholders.

Define project objectives, identify project deliverables, create a work breakdown structure (WBS), define project scope boundaries, obtain approval from stakeholders.

Define project objectives, identify project deliverables, create a work breakdown structure (WBS), define project scope boundaries, ignore approval from stakeholders.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the key elements to consider when defining project scope?

Project objectives, budget, timeline

Team members, office location, project duration

Project objectives, deliverables, milestones, budget, timeline, resources, risks, and constraints.

Stakeholders, project scope, communication plan

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?