1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Rock fill placement recommendations shall apply if more than 80% of the material is larger than the 4-in. sieve.
True
.False
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To reduce the potential for differential settlement on this project each pad shall be overexcavated a minimum of 36 in. and replaced with engineered fill.
.True
False
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In preparation for a project—just before grading—it is wise to pick up samples of both native and import soils (if known) for Proctor analysis.
.True
False
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The sequence of density tests on a project must be started over on a daily basis beginning at number 1.
True
.False
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Density test number 142 failed last week, but a retest taken at the same location today passed; however, the last passing test number is now number 215. What is the proper designation for a passing retest of number 142?
.142R
142
216
None of the above
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?