1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A surveying instructor sent out six groups of students to measure a distance between two points on the ground. The students came up with the following six different values: 150.52, 150.35, 150.89, 150.02, 150.98 and 150.78. Assuming these values are equally reliable and that variations results from accidental errors, determine the most probable value of the distance measured.
150.49
150.59
150.69
150.79
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Estimate the actual bucket load in bank cubic meters for loader bucket whose heaped capacity is 3.82 m3. The soil's bucket fill factor is 0.9 and its load factor is 0.8.
1.75 BCM
2.75 BCM
3.75 BCM
4.75 BCM
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Initially, the number of bacteria present in a culture is No. At t = 1 hour the number of bacteria is measured to be 3/2 No. If the rate of growth is assumed to be proportional to the number of bacteria present, determine the time necessary for the number of bacteria to triple.
1.7 hrs
2.7 hrs
3.7 hrs
4.7 hrs
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The distance between the entrance and exit points on a horizontal circular roadway curve is 747 ft. The radius of the curve is 400 ft. Determine the central angle between the entrance and exit points.
107 deg
117 deg
127 deg
137 deg
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
It is known that 80 percent of all families won a television set. If 10 families are interviewed at random, find the probability that 7 families own a television set.
0.102
0.120
0.201
0.210
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The probability that a freshman entering a university will graduate after a four-year program is 0.6. If 1000 students enroll at university, find the standard deviation of the number of students who graduated.
15.49
15.94
51.49
51.94
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Megan is a recent civil engineering graduate. One of her first job is to calculate a bridge cost using the following data. The first cost will be $49,000, the annual operating costs for energy and maintenance will be $15,000, the expected life in 10 years, the expected salvage value is 0 and the firm's interest rate is 9%. What is EAC?
$22.6k
$26.2k
$26.6k
$22.2k
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
16 questions
Math Pretest
Quiz
•
Professional Development
20 questions
Examen de matemáticas 1
Quiz
•
Professional Development
20 questions
Review measure of Central Tendency
Quiz
•
4th Grade - Professio...
15 questions
Balance Equations Hangers
Quiz
•
Professional Development
20 questions
Reasoning & Aptitude
Quiz
•
Professional Development
20 questions
Matematika SMP (dasar)
Quiz
•
Professional Development
15 questions
Mathematics Form 3
Quiz
•
9th Grade - Professio...
15 questions
Pola Barisan dan Bilangan (2)
Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade