PJMT 2103: Week 5: PM Time Management

PJMT 2103: Week 5: PM Time Management

University

10 Qs

quiz-placeholder

Similar activities

Love Live! Quiz

Love Live! Quiz

7th Grade - University

10 Qs

2025  Ed Puzzle Leadership and Small Group Work Training Quiz

2025 Ed Puzzle Leadership and Small Group Work Training Quiz

8th Grade - University

14 Qs

Prelim Examination in NSTP 2  Part 1

Prelim Examination in NSTP 2 Part 1

University

12 Qs

PMIT Chapter 2

PMIT Chapter 2

University

10 Qs

Project Cost Management

Project Cost Management

University

10 Qs

Week 1 & 2 - Project Management

Week 1 & 2 - Project Management

University

10 Qs

quiz on PERT

quiz on PERT

University

15 Qs

Quality in Construction

Quality in Construction

University

11 Qs

PJMT 2103: Week 5: PM Time Management

PJMT 2103: Week 5: PM Time Management

Assessment

Quiz

Other

University

Easy

Created by

Jennifer Labatte

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the definition of Project Time Management?

Risk assessment for the project

Ensuring the timely completion of the project

Managing project resources

Quality control of project deliverables

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Kiara, Chloe, and Samuel are planning a school event. What is involved in their activity definition?

Identifying and documenting the activities they need to carry out for the event

Estimating the budget for the event

Conducting a market analysis for the event

Building a team for the event

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Ellie, James, and Kiara are working on a school project. What does their task of Activity Sequencing involve?

Identifying and documenting interactivity logical relationships

Resource allocation for the project

Marketing strategy development

Financial analysis for the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Noah, Mia, and Neha are working on a school project. They are trying to figure out how long each task will take to complete. What is this process called?

Managing stakeholders for their project

Ensuring quality assurance for their project activities

Developing / estimating durations for each task to create a schedule

Ensuring legal compliance for their project

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Schedule Development in project management?

Risk assessment for the project

Quality control of project deliverables

Team building for the project

Determining start and finish dates for project activities

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Thomas, Aiden, and Oliver are working on a group project. What is Thomas, who is in charge of Schedule Control, primarily concerned with?

Conducting financial analysis for the project

Influencing factors that create schedule changes

Developing a marketing strategy for the project

Allocating resources for the project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Olivia, Chloe, and Arjun are working on a project. They have defined activity processes and are making up of activities. What is the output of their defined activity processes?

Activity list

Task list

Resource list

Budget list

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?