TOPIC 1 : PROJECT PLANNING & SCHEDULING

TOPIC 1 : PROJECT PLANNING & SCHEDULING

University

10 Qs

quiz-placeholder

Similar activities

REVIT 4 WEEK1

REVIT 4 WEEK1

University

12 Qs

S1 Mixed-used development

S1 Mixed-used development

University

12 Qs

Shymkent

Shymkent

University

8 Qs

OFFICE PROJECT MANAGEMENT

OFFICE PROJECT MANAGEMENT

University

11 Qs

Building Information Modelling Quiz

Building Information Modelling Quiz

University

14 Qs

S4.1 Return Brief & Fee Proposal

S4.1 Return Brief & Fee Proposal

University

11 Qs

revit structure

revit structure

University

10 Qs

ARCHITECTURAL Quiz

ARCHITECTURAL Quiz

1st Grade - University

10 Qs

TOPIC 1 : PROJECT PLANNING & SCHEDULING

TOPIC 1 : PROJECT PLANNING & SCHEDULING

Assessment

Quiz

Architecture

University

Hard

Created by

Izza Noor

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

FILL IN THE BLANK QUESTION

10 sec • 10 pts

Project planning is the systematic process of organizing and _________ the required activities in order to ensure the project is completed.

2.

MULTIPLE CHOICE QUESTION

10 sec • 10 pts

Define the project which is use to identify the cumulative cost or work progress of project over time

Project ES Curve

Project SS Curve

Project S Curve

Project Curve

3.

MULTIPLE CHOICE QUESTION

10 sec • 10 pts

Media Image

Based on Graph 1, define the element in X-Axis

Work Progress

Timeline

Cumulative Value

Cost

4.

MULTIPLE SELECT QUESTION

10 sec • 10 pts

Who are the stakeholder involved in project planning?

Owner

Client

Clerk

Supplier

5.

MULTIPLE CHOICE QUESTION

10 sec • 10 pts

Choose four (4) process of Project Planning in sequence

Project Overview > Task Identification > Resource Allocation > Project Scheduling

Project Overview > Project Scope > Task Identification > Project Scheduling

Project Overview > Task Identification > Risk Management > Project Scheduling

Project Overview > Task Identification > Budget Control > Project Scheduling

6.

MULTIPLE CHOICE QUESTION

10 sec • 10 pts

''Raining and flood could cause of weather delay during construction''

Based on statement above, identify the process of project planning

Task Identification

Monitoring and Controlling

Project Scheduling

Risk Management

7.

MULTIPLE SELECT QUESTION

10 sec • 10 pts

Choose the project materials used in construction or development process

Bricks

Concrete

Carpet

Floor Tiles

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?