Project Management - Lesson 3  Quiz

Project Management - Lesson 3 Quiz

12th Grade

13 Qs

quiz-placeholder

Similar activities

2.01 Project management 1

2.01 Project management 1

9th - 12th Grade

11 Qs

PM 1 1.02 Quizizz

PM 1 1.02 Quizizz

9th - 12th Grade

15 Qs

B.E.S Quiz

B.E.S Quiz

12th Grade

10 Qs

Prioritizing Work

Prioritizing Work

9th - 12th Grade

12 Qs

Chapter 5 Business Organizations

Chapter 5 Business Organizations

9th - 12th Grade

10 Qs

PM1 - 1.04 (FHS - Moffitt)

PM1 - 1.04 (FHS - Moffitt)

12th Grade

15 Qs

Year 11 Preliminary HSC: Business Management

Year 11 Preliminary HSC: Business Management

12th Grade

15 Qs

CLO Business Studies: Boston Matrix Quiz

CLO Business Studies: Boston Matrix Quiz

9th - 12th Grade

10 Qs

Project Management - Lesson 3  Quiz

Project Management - Lesson 3 Quiz

Assessment

Quiz

Business

12th Grade

Easy

Created by

Yến Điền

Used 1+ times

FREE Resource

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which organizational form is it most difficult to integrate project activities?

Classical/traditional

Projectized

Strong matrix

Weak matrix

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which organization form would the project manager possess the greatest amount of authority?

Classical/traditional

Projectized

Strong matrix

Weak matrix

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which organizational form does the project manager often have the least amount of authority?

Classical/traditional

Projectized

Strong matrix

Weak matrix

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which organizational form is the project manager least likely to share resources with other projects?

Classical/traditional

Projectized

Strong matrix

Weak matrix

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which organizational form do project managers have the greatest likelihood of possessing reward power and have a wage-and-salary administration function? (The project and line manager are the same person.)

Classical/traditional

Projectized

Strong matrix

Weak matrix

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which organizational form is the worker in the greatest jeopardy of losing his or her job if the project gets canceled?

Classical/traditional

Projectized

Strong matrix

Weak matrix

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which type of matrix structure would a project manager most likely have a command of technology?

Strong matrix

Balanced matrix

Weak matrix

Cross-cultural matrix

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?